Initial Start-Up - Pfaff 3519-5/01 Instruction Manual

Table of Contents

Advertisement

Set-up and Initial Start-up
8

Initial start-up

.02
● Before the initial start-up, clean the machine thoroughly and lubricate or fill the oil, see
● Inspect the machine and in particular the electric lines and pneumatic connecting hoses
● Arrange for technical staff to check whether the machine may be operated at the existing
24
chapter 12 Maintenance and Care!
for possible damage.
mains voltage and whether it is connected properly.
Do not operate the machine if there are any differences!
The machine must only be connected to a grounded socket!
Fig. 8 - 07
● Connect the machine to the compressed
air system and push the slide closure 1
upwards.
● It must have a supply pressure of 6 bar.
Set this value if necessary, see chap-
ter 12.06 Monitoring / adjusting the air
pressure.
1

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents