BASIC TOOLS AND MATERIALS NEEDED

• Medium Phillips head screwdriver (#2) (recommended magnetized tip)
• ESD wrist band
Recommended, but not required:
• Torque screwdriver (30 inch-pounds/3.4 Newton-Meters capacity)
®
• Loctite
262 (Red) for use on lock case mounting screws
WARNING: Kaba Mas locks are protected from 25,000 V Electrostatic Discharge
(ESD) damage when correctly installed. Follow these precautions to avoid ESD
damage when installing the lock:
• Handle the keypad assembly by the outer edge only.
• Use an ESD wrist band grounded to the lock or container during installation.
DESIGN PARAMETERS FOR MOTORIZED DEAD BOLT LOCKS
1. Bolt dimensions (nominal): .312 inches x 1.000 inches/8 x 25.4mm
2. Bolt movement (nominal): .465 inches/11.8mm
3. Bolt extension: .465 inches/11.8mm
4. Maximum load movable by the bolt: 6.7 lbs. (30N)
Motorized Dead Bolt locks may not open if more than 6.7 lbs. (30N) of
NOTE:
force is applied to the end or side of the bolt.
5. Maximum load against bolt when thrown (all directions): 224.8 lbs. (1kN)
6. The lock can be itted to safes or vault doors of any material.
As is the case with all mechanical and electronic locking devices, the
NOTE:
container and boltworks must be designed to protect the lock.

PREPARE FOR NEW INSTALLATION OF THE LOCK

1. Using the lock parts along with the template provided, establish the exact
location for the drilled and tapped holes. For the Motorized Dead Bolt, only 3 of
the 4 mounting holes are required.
Caution: The lock case must be mounted exactly according to the template if
mounted over the cable routing hole. Otherwise, the lock case must be mounted
so that no part of the case covers the cable routing hole.
2. The cable hole diameter can be a minimum of .406" (10.3mm) to a maximum of
.438" (11.1mm). The .406" (10.3mm) diameter is recommended. The cable hole
must be deburred.
3. The dial assembly mounting screws require drilled and tapped holes to 3/8"
(9.5mm) depth if possible (minimum 1/4" or 6.4mm depth required.) Drill either
the two horizontal mounting holes or the two vertical holes.
4. When mounting the lock unit (i.e., integrating it into a boltwork), make sure the
lock bolt has clearance to freely move to its end positions and the shifting force
works only in the axial direction (direction of movement). Lateral forces should
not be exerted on the lock.