Pre-Start-Up Checklist

Every installation requires a comprehensive start-up
to ensure proper operation of the unit. As part of that
process, the following checklist must be completed and
information recorded. Starting up the unit in accordance
with this checklist will not only ensure proper operation,
but will also provide valuable information to personnel
performing future maintenance. Should an issue arise
which requires factory assistance, this completed
document will allow unit experts to provide quicker
resolve. Qualified personnel should perform start-up to
ensure safe and proper practices are followed.
Unit Model No. __________________________________
Unit Serial No. ____________________________________
Energy Wheel Date Code __________________________
Start-Up Date ____________________________________
Start-Up Personnel Name _________________________
Start-Up Company ________________________________
Phone Number ___________________________________

Start-Up Checklist

Line Voltage. Check at unit disconnect.
Motor Amp Draw
Supply Motor Amps
Exhaust Motor Amps
Fan RPM
Supply Fan
Measured Airflow
Exhaust Fan
Measured Airflow
Energy Wheel Motor
14
Model APEX Energy Recovery Ventilator
L1-L2
Volts
L1
Amps
L1
Amps
RPM
CFM
RPM
CFM
L1
Amps
 Disconnect and lock-out all power switches.
 Remove any foreign objects that are located in the
energy recovery unit.
 Check all fasteners, set-screws, and locking collars
on the fans, bearings, drives, motor bases and
accessories for tightness.
 Check fan rotation.
 Rotate the fan wheels and energy recovery wheels
by hand to ensure no parts are rubbing.
 Check the fan belt drives for proper alignment and
tension.
 Filters can load up with dirt during building
construction. Replace any dirty pleated filters and
clean the aluminum mesh filters in the intake hood.
 Verify that non-motorized dampers open and close
properly.
 Check the tightness of all electrical wiring
connections.
 Verify control wire gauge.
 Verify diameter seal settings on the energy recovery
wheel.
 Verify proper drain trap installation.
 Inspect all coils within the unit. Fins may get
damaged in transit or during construction. Carefully
straighten fins with a fin comb.
L2-L3
Volts
L2
Amps
L2
Amps
Correct fan rotation direction?
Supply Fan
Yes / No
Exhaust Fan
Yes / No
L2
Amps
L1-L3
Volts
L3
Amps
L3
Amps
L3
Amps
®