Commissioning

7.2 Commissioning the SIPROCESS GA700

7.2
Commissioning the SIPROCESS GA700
Procedure
Product designation
Version of the device firmware
Progress bar
Figure 7-1
Splash screen
1. Supply the device with power. Information on power supply of the device is available in
2. Scan of basic settings:
3. Wait for transition to warming-up phase:
42
the device-specific documentation. See: Table A-3 LVZ3 (Page 81).
The boot process starts. The splash screen is initially visible on the device display.
The boot process is interrupted momentarily. Two successively displayed editing windows
prompt you to select the display language and to enter the date and time.
– Select one of the offered language options in the first editing window.
– Then set the date and time of day.
Once you have entered the requested information, the boot process continues.
When the splash screen disappears, the device is in the warming-up phase. The current
temperature status is displayed as a bar graph in the warming-up window.