3 Upon Reception

3.1

What this chapter contains

This chapter gives basic information on how to inspect, transport, identify and store the
PQFM active filter.
3.2

Delivery inspection

Each PQFM is delivered in an enclosure designed to protect adequately the equipment
during shipment. Upon reception of the equipment, make sure that the packing is in
good condition. Verify the state of the shock and tilting indicators (if mounted on the
enclosure).
After removal of the packing, check visually the exterior and interior of your filter for
transportation damage.
Your filter equipment comes with an information package that is present in a
documentation holder attached at each filter panel. Verify that all documentation is
present, i.e.:
-
this manual
-
the electrical drawing and connection diagram
-
the communication cable needed for multi-unit operation
For slave units, an interconnection seal and interconnection pads are also provided.
For plate versions of filter (IP00-versions) the following hardware components are also
provided:
-
the PQF-Manager user interface with connection lead;
-
optional components.
Any loss or damage should be notified immediately to your ABB representative.
3.3

Lifting and transportation guidelines

Please note that filter equipment weighs hundreds of kilograms. Care should be taken
to ensure that correct handling facilities are used. For individual cubicles the lifting lugs
should be employed.
Manual Power Quality Filter PQFM ç Upon Reception 9