1. Position the lift device next to the director.
2. Using a pallet jack, raise the pallet on which the director is mounted to the
3. Slide the director across from the pallet to the lift device.
4. Determine the appropriate rack-mount position. Remember that the director is

HP 9000, HP 10000, and HP 11000 Series Rack Installation

To install the director in an HP 9000, HP 10000, or HP 11000 Series Rack,
complete the procedures in the following sections:

Install the Shelf Brackets in a HP 9000, HP 10000, and HP 11000 Series Rack

Use these steps to install the two shelf brackets in the rack.
Note:
accessibility to the cables entering and exiting the rack.
1. Determine the appropriate placement for the switch inside the rack. It is
Director 2/64 Installation Guide
WARNING:
The Director weighs approximately 115 pounds. Use proper
handling and lifting equipment to reduce the possibility of injury or product
damage.
Two people will need to work together to transfer the director to the lift. Make
sure the wheels of the lift cannot roll as you transfer the director to the lift.
Move the director slowly and carefully onto the lift to prevent back and hand
injury. Dropping the director could injure personnel or damage the equipment.
same height as the top surface of the lift device.
9U (15.75 inches) high.
Install the Shelf Brackets in a HP 9000, HP 10000, and HP 11000 Series
Rack, page 47
Prepare the Switch for
Finalize the Rack-Mounting
Consider leaving the bottom and top U positions open to permit easy
important to consider the number of switches you intend to install. See
for Installing More than One
Installation, page 48
Procedure, page 51
Switch" on page 46.
Installing and Configuring the Director
"Tips
47