1.4 Guide for Commissioning of ET 200S with Fail-Safe Modules

1.4
Guide for Commissioning of ET 200S with Fail-Safe Modules
Introduction
The following table lists all the important steps required for commissioning ET 200S
distributed I/O systems with fail-safe modules as DP slaves/IO devices on
PROFIBUS DP/PROFINET IO.
Steps from Selecting the F-Modules to Commissioning the ET 200S
Table 1- 3
Step
1.
2.
3.
4.
5.
6.
7.
Note
You must configure and assign parameters to the F-modules in
commissioning.
Reason:
must set these PROFIsafe addresses by means of switches on all F-modules prior to their
installation.
18
Steps from Selecting the F-Modules to Commissioning the ET 200S
Procedure
Select F-modules for ET 200S configuration "Configuring" chapter
Configure and assign parameters to F-
STEP 7
modules in
Set PROFIsafe addresses on F-modules
Install ET 200S
Wire the ET 200S
Commission ET 200S on
PROFIBUS DP/PROFINET IO
Run diagnostics on ET 200S if
commissioning failed
STEP 7
automatically assigns the PROFIsafe addresses to the F-modules. You
See ...
"Configuration and Parameter Assignment"
and "Fail-Safe Modules" chapters
"Address Assignment and Installation"
chapter
"Address Assignment and Installation"
chapter
"Wiring and Fitting Modules" chapter
ET 200S Distributed I/O System
instructions
"Diagnostics" chapter, "Fail-Safe Modules"
ET 200S Distributed I/O System
chapter and
operating instructions
STEP 7
ET 200S Distributed I/O System - Fail-Safe Modules
Installation and Operating Manual, 08/2008, A5E00103686-07
operating
before you start

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents