3.4

Installation and Wiring with an Power Xpert 9395 UPS

Eaton 9315/9390/9395 Fixed Master Sync Control Installation and Operation Manual
NOTE When installing wiring connections, conduit must be installed between the Eaton Fixed Master Sync
Control and the UPS cabinet. Conduit also must be installed between the Eaton Fixed Master Sync Control and the
customer's remote monitoring system.
To install and wire:
1.
Install the Eaton Fixed Master Sync Control panel to the selected mounting
location.
See Figure 2‐1 on page 2-2 for mounting hole dimensions and Figure 2‐2 on
page 2-3 for conduit entrance locations.
2.
Unfasten the front door latches and swing the door open.
3.
Complete all control wiring interconnections using Table 3‐8 for wiring
requirements.
Figure 3‐2 shows the Eaton Fixed Master Sync Control TB1 terminal block and
ground terminal locations. Figure 3‐3 shows the TB1 terminal block wiring detail.
Figure 3‐15 through Figure 3‐18 show the typical locations of the UPS TB3, TB6,
and X-Slot
Relay Interface Card interconnect terminal blocks. Figure 3‐14 shows
®
the TB6 detail.
Refer to the applicable Power Xpert 9395 UPS Installation and Operation Manual
listed in paragraph 1.3 on page 1-4 for UPS cabinet terminal locations and
assignments, termination requirements, conduit landing locations, and terminal
access instructions.
NOTE Complete the wiring to the X-Slot Relay Interface Card terminals before installing the cards in the
Communication Bay in each of the UPS cabinets.
4.
Route wires through the strain relief bushing and connect to the terminals on the
X-Slot Relay Interface Card in each of the UPS cabinets (see Figure 3‐19 and
Figure 3‐20).
5.
Install the X-Slot Relay Interface Card into an open X-Slot communication bay on
the front of the UPS (see Figure 3‐15, Figure 3‐16, Figure 3‐17, or Figure 3‐18).
Refer to the applicable Power Xpert 9395 UPS Installation and Operation Manual
listed in paragraph 1.3 on page 1-4 for UPS cabinet access instructions.
6.
Verify the jumper is installed between Sync Control terminal TB1-40 and TB1-41
(see Figure 3‐3).
7.
When all wiring is complete, close the door and secure the latch.
When connecting the bypass and load voltage from another model UPS to a Power Xpert 9395 UPS using the
Eaton Fixed Master Sync Control accessory, use Phase A, Phase B, and Neutral connections from the other UPS.
DO NOT connect the other model UPS Phase C bypass and load voltage to the Sync Control connection point
when connecting to an Power Xpert 9395 UPS.
C A U T I O N
S
P-164000023 Rev 1 www.eaton.com/powerquality
INSTALLATION
3-19

Advertisement

Table of Contents
loading

This manual is also suitable for:

93909395

Table of Contents