Step 6 — Install Field Insulation
CAUTION
Protect insulation from weld heat damage and weld splat-
ter. Cover with wet canvas cover during water piping
installation.
When installing insulation at the jobsite, insulate the follow-
ing components:
• compressor motor
• economizer
COND.
COOLER
DRIVE END VIEW
• cooler shell
• cooler tube sheets
• suction piping
• motor cooling drain
• oil reclaim piping
• oil cooler refrigerant side tubing
• refrigerant liquid line to cooler
NOTE: Insulation of the waterbox covers is applied only at the
jobsite by the contractor. When insulating the covers, make
sure there is access for removal of waterbox covers for servic-
ing. See Fig. 37.
TOP VIEW
FRONT VIEW
FACTORY INSTALLED INSULATION
FIELD SUPPLIED AND INSTALLED
INSULATION (IF REQUIRED)
Fig. 37 — 19XR Insulation Area
63
COND.
COOLER
COMPRESSOR END VIEW