Testing functionality by secondary injection
10.4.12.2
10.4.13
10.4.13.1
108
5.
Increase the current to 100% of IBase.
6.
Switch the current off and measure the time for activation of TRIP1, trip of stage
1.
7.
If a second stage is used, repeat steps

Completing the test

Continue to test another function or end the test by changing the TestMode setting to
Off. Restore connections and settings to their original values, if they were changed for
testing purposes.

Directional overpower protection GOPPDOP

Prepare the IED for verification of settings outlined in section
verify
settings".

Verifying the settings

The overpower protection shall be set to values according to the real set values to be
used. The test is made by means of injection of voltage and current where the
amplitude of both current and voltage and the phase angle between the voltage and
current can be controlled. During the test the analog outputs of active and reactive
power shall be monitored.
1.
Connect the test set for injection of voltage and current corresponding to the
mode to be used in the application. If a three phase test set is available this could
be used for all the modes. If a single phase current/voltage test set is available the
test set should be connected to a selected input for one phase current and voltage.
2.
Adjust the injected current and voltage to the set rated values in % of IBase and
UBase (converted to secondary current and voltage). The angle between the
injected current and voltage shall be set equal to the set direction Angle1, angle
for stage 1 (equal to 0° for low forward power protection and equal to 180° for
reverse power protection). Check that the monitored active power is equal to
100% of rated power and that the reactive power is equal to 0% of rated power.
3.
Change the angle between the injected current and voltage to Angle1 + 90°.
Check that the monitored active power is equal to 0% of rated power and that the
reactive power is equal to 100% of rated power.
4.
Change the angle between the injected current and voltage back to Angle1 value.
Increase the current slowly from 0 until the START1 signal, start of stage 1, is
activated. Check the injected power and compare it to the set value Power1,
power setting for stage 1 in % of Sbase.
5.
Increase the current to 100% of IBase and switch the current off.
6.
Switch the current on and measure the time for activation of TRIP1, trip of stage
1.
7.
If a second stage is used, repeat steps
1MRK 511 360-UEN A
2
to
6
for the second stage.
"Preparing the IED to
2
to
6
for the second stage.
Bay control REC670 2.1 IEC
Commissioning manual