About This Manual

This section describes important information about the design of this document.

Purpose

The purpose of this document, Juniper Networks G10 CMTS Pre-Installation Guide, is to
describe the installation site requirements that must be met prior to installing the G10 Cable
Modem Termination System (CMTS). The requirements and recommendations given are
prerequisites to those instructions provided in the Juniper Networks G10 CMTS Installation and
Configuration manual.
The intended audience for this information consists of individuals involved in preparing an
installation site for equipment installation or involved in installing the G10 CMTS.

Organization

This document is organized as follows:
"Safety" – Provides recommendations to ensure the safety and protection of system
equipment and equipment installers.
"Notices" – Lists important UL, EN and FCC notices.
"Power" – Provides input power requirements for the AC and DC configuration options
of the CMTS.
"Environment" – Provides specifications for maintaining proper environmental
conditions for the CMTS.
"Mounting" – Provides recommendations for mounting the CMTS in an equipment
rack, including the organization of cabling, thermal management considerations, and
positioning of the rack to allow sufficient access clearance.
"Tools and Equipment Required for Installation" – Provides information regarding
the tools, supplies, and equipment recommended for installing the CMTS.
"Characterization of Installation Site" – Provides a set of parameters relative to
aspects of the installation site system, HFC network connections, and CMTS
downstream and upstream transmissions. These parameters are to be characterized
prior to the installation of the CMTS.