Gas supply

Gas pipe sizing must consider the gas input to this appliance as well as all other gas
appliances in the premises. The gas meter and regulator must be specified for the total
gas rate. An approved sizing chart such as the one in AS/NZS 5601.1 should be used.
The gas supply termination is inside the heater and enters through the rear of the
appliance.
Gas supply location
1. Mark off the location for the vertical centre line of the
heater enclosure.
2. To the right of the vertical centre line, mark off the
vertical  and horizontal  locations for the gas supply
penetration.
INBUILT
Masonry
305 mm to right of the
appliance centre line
45 mm from base of
enclosure
Terminate 230 mm from
front of enclosure
sTEP 1
Inbuilt installations
4
The length of the gas supply termination
is measured from the front of the
enclosure.
Mock chimney
305 mm to right of the
appliance centre line
45 mm from base of
enclosure
Terminate 230 mm from
front of enclosure
Freestanding installations
The length of the gas supply termination
is measured from the back of the heater
plus 125 mm.
Gas supply location
FREEsTANDING
Console
305 mm to right of the
appliance centre line
140 mm from floor level 215 mm from floor level
Terminate at wall,
clearance plus 125 mm
sTEP 2
4
Installer to terminate to suit, and fit
supplied gas connection . Leak test the
joint between the flexible gas connection
and termination.
2
3
Plinth
305 mm to right of the
appliance centre line
Terminate at wall,
clearance plus 125 mm
5
Neo installation guide: 11906-H 08-15 | 13

Advertisement

Table of Contents
loading

This manual is also suitable for:

Neo rib2311n

Table of Contents