When installing the mower the following assembly
operations must also be completed.

Install Mower Mounts

1.
Check length or strut, adjust to 15" if required
(Fig. 8).
2.
Attach left and right struts, with greases fitting
up. Secure inside of rear frame member with
5/8–11 x 5" (127 mm) bolts, 5/8" lock washers
and 5/8–11 nuts (Fig. 8).
4
3
1
Figure 8
1. Strut
2. Bolt 5/8–11 x 5" (127 mm)
3. Lock washer 5/8"
3.
Remove one 7/16–14 flange nut from bolt in
each chain assembly (Fig. 9).
4.
Place bolt of chain into traction unit lift arm slot
and secure with previously removed 7/16–14
flange nut (Fig. 9). Tighten flange nut securely.
2
3
Figure 9
1. Lift chain assembly
2. Flange nut 7/16–14
2
5

4. Nut 5/8 11

5. 15" dimention
3
1
m–3686
3. Lift arm
Install Power Take Off (PTO)
Spring
5.
Install the PTO clutch spring. Hook one end
around frame bolt, between washer and spacer
(Fig 10). Stretch spring and hook other end to
the PTO idler arm.
6.
Install and adjust PTO Drive belt, refer to
Replacing the PTO Drive Belt.
2
1
4
Figure 10
1. Spring
2. Washer
Assembly
3
m–3689
3. Spacer
4. PTO idler arm
15

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Z-252

Table of Contents