1.3
Instructions for storage, transport and handling of the unit

1.3.2 Hoisting points

The points designed for hoisting the unit are located
on the beams on its base -arrows-.
Install 5/8" shackles -A- on the points designed for
hoisting.
A T T E N T I O N
Do not use fork lifts in operations to load and unload
the unit.
Before hoisting the unit, check that the cables or
slings are firmly hooked to these points and make
sure the crane and the cables or slings are capable of
lifting the weight.
See the weight in the technical data table or on the
rating plate.
Do not forget to include the weight of the options
installed in the unit.
Place spacers -1- at the top of the unit to prevent the
cables or slings from touching it.
Attach guide ropes so that the unit does not rotate
freely.
The cables or slings should be long enough to form
an angle of over 45° to the horizontal plane. Hoist the
unit keeping it in a horizontal position.
D A N G E R
There should not be onlookers within a radius of 10
m of the unit when it is being hoisted.