Operation Of Furnace During Construction; Installation In A Garage; Clearances To Combustible Materials - Nordyne SC Installation Instructions Manual

Single stage condensing gas furnaces
Table of Contents

Advertisement

Installation in a Garage

WARNING:
Do not place combustible material on or against
the furnace cabinet or within 6 inches of the
vent pipe. Do not place combustible materials,
including gasoline or any other flammable
vapors and liquids,in the vicinity of the furnace.
This gas-fired furnace may be installed in a residential
garage with the provision that the burners and igniter
are located no less than 18 inches (457mm) above the
floor. The furnace must be located or protected to prevent
physical damage by vehicles.

Clearances to Combustible Materials

This furnace is Design Certified in the U.S. and Canada
by CSA International for the minimum clearances to
combustible materials. NOTE: The furnace is listed for
installation on combustible or non-combustible flooring.
However, wood is the only combustible flooring allowed
for installation. Downflow models must use the appropriate
subase kit when installing over a wood floor. To obtain
model number and specific clearance information, refer
to the furnace rating plate, located inside of the furnace
cabinet.
Access for positioning and servicing the unit must be
considered when locating unit. The need to provide
clearance for access to panels or doors may require
clearance distances over and above the requirements.
Allow 24 inches minimum clearance from the front of
the unit. However 36 inches is strongly recommended.
See
Figure 1
for minimum clearance requirements.
CLEARANCES TO COMBUSTIBLE MATERIALS
UPFLOW
APPLICATIONS
BACK
HORIZONTAL
APPLICATIONS
TOP
FRONT
Left Side..................0 Inches Top ..........................0 Inches
Right Side ...............0 Inches Front ......................
Vent .........................0 Inches Back ........................0 Inches
Allow 24 in. minimum clearance for servicing. Recommended
clearance is 36 in.
Figure 1. Minimum Clearances to
Combustible Materials
6
DOWNFLOW
APPLICATIONS
BACK
SIDE
TOP
FRONT
SIDE
FRONT
4 Inches

Operation of Furnace During Construction

CAUTION:
Failure to follow these instructions will void the
factory warranty and may significantly reduce
the life or the performance of the furnace, and/
or result in other unsafe conditions. It is the
responsibility of the installing contractor to
insure these provisions are met.
Operating gas furnaces in construction environments can
cause a variety of problems with the furnace. Proper use
of commercial portable space heating equipment during
construction is recommended. This gas furnace may be
used during construction if it is not in violation of any
applicable codes and the following criteria are met:
• The installation must meet all applicable codes. The
furnace must be permanently installed according to the
instructions supplied with the furnace including electrical
supply, gas supply, duct work and venting. The furnace
must be controlled by a thermostat properly installed
according to the instructions supplied with the furnace
and thermostat. The installation must include a properly
installed filter in the return air system with no by-pass
air. The filter must be inspected frequently and replaced
when necessary.
• Combustion air must be supplied from outside the
structure and located such that dust and gases
from construction activity are not introduced into the
combustion system.
• Provisions must be made to insure that condensate
does not freeze in the furnace or condensate drain lines
during operation and during idle times; for example,
overnight if turned off.
• Before occupying the structure: The filter must be
replaced or cleaned, the duct work must be inspected
and cleaned of any construction debris, and the furnace
must be cleaned and/or repaired if found to be dirty,
damaged, or malfunctioning in any way by a qualified
HVAC technician. The furnace shall be inspected and
approved by applicable local authority even if this
requires redundant inspections.
• Serial numbers for furnaces used during construction
must be submitted in writing (fax and email also
acceptable). This information will be used to track the
long-term affects of the use during construction on
furnaces. Proof of this submittal shall be available for
the final inspection of the furnace prior to occupancy.
• This furnace is designed to operate with return air
temperatures in ranges normally found in occupied
residences, including setbacks. Minimum continuous
return temperature must not be below 60° F (15° C).
Occasionally a temporary return temperature of 55° F
(12° C) is acceptable. However, operation with a return
temperature below 55° F (12° C) is not allowed.

Advertisement