Determine the chimney components needed to complete
your particular installation:
•
Measure the total vertical height of the fireplace
installation from the base of the fi replace assembly to
the approximate location of the bottom of the termination
cap.
•
Subtract the effective height of the fi replace assembly
(see Figure 4.1) from the total vertical height to determine
the overall height of the chimney installation.
•
Create a schematic for your application similar to Figure
4.1 showing components required (referring to Table 4.1).
•
Install a ceiling fi restop whenever the chimney penetrates
a fl oor/ceiling.
NOTICE:
A maximum of two offset and return may be
used.
CAUTION! Risk of Fire and/or Asphyxiation! DO
NOT connect this fi replace to a chimney fl ue servicing
another appliance. Do NOT connect to any air distribu-
tion duct or system. These actions could cause over-
heating/fi re in the chimney fl ue, or release of exhaust
fumes into the living areas.
16
Heatilator • Birmingham BIR50-B Installation Manual • 4059-701 • Rev B • 2/6/13
Termination
Cap
Storm
Collar
Chase Top
Flashing
74 1/8 in.
(1883 mm)
Effective
Height
Figure 4.1
(4) Roof
Radiation
Shields
Chimney Section
Attic Insulation
Shield & Collar
Square Frame
Firestop
Chimney Section
Square Frame
Firestop
Chimney Section