Removal of
Procedure
before disassembling work.
Step
1. Removing the tie wires
1
The figure shows the tie
pipe connections.
2
Remove the terminal
board fitting screw.
Removal Procedure
Electrical BOX
Warning
Be sure to wait 10 minutes or more after turning off all power supplies
Procedure
Outdoor Unit (52 / 58 / 68 / 75 Class)
Points
Remove the piping in the
backward direction.
Match the colours of the tie
wires to A, B, C and D ports
as follows.
(1) - Black Power
(2) - White Power
(3) - Red Transmission
Wires are fixed to the
terminal board with screws.
Terminal board is made of
integral moulded resin.