NOTE: There must be NO INSULATION or other
combustibles inside the framed firestop opening.
CEILING
NAILS (4 REQUIRED)
Figure 25. Ceiling Firestop (Ceiling Side)
If the area above the ceiling IS an attic, position and secure
the firestop on top of the previously framed hole.
NOTE: Keep insulation away from the vent pipe at least
1 inch (25mm).
CEILING
CEILING FIRESTOP
Figure 26.
Attic Firestop
JOIST
CEILING FIRESTOP
NAILS (4 REQUIRED)
RAFTER
Quadra-Fire • QV36DB • 2017-900 Rev. C • 5/05
C. Vent Termination
Refer to Cinch Pipe and Termination Cap installation in-
structions.
Horizontal Termination
• The termination kit should pass through the wall firestops
from the exterior of the building.
• Adjust the termination cap to its final exterior position
on the building and interlock the flue sections.
WARNING: THE TERMINATION CAP MUST BE
!
POSITIONED SO THAT THE ARROW IS POINTING
UP.
WARNING: VENTING TERMINALS SHALL NOT
!
BE RECESSED INTO A WALL OR SIDING. VENT
TERMINATION CLEARANCES MUST BE FOL-
LOWED TO AVOID FIRE DANGER. SEE VENT TER-
MINATION MINIMUM CLEARANCES DIAGRAM ON
FOLLOWING PAGE.
Figure 27. Trapezoid Termination Cap
7 1/4"