Modulating gas-fired, low intensity unitary heater
Table of Contents

Advertisement

EM-S
I
, O
ERIES
NSTALLATION
PERATION AND
service or maintenance. Allow heater to cool before
servicing.
Before every heating season, a contractor qualified in
the installation and service of gas-fired heating
equipment must perform a thorough safety
inspection of the heater.
For best performance, the gas, electrical, thermostat
connections, tubing, venting, suspensions and
overall heater condition should be thoroughly
inspected.
NOTE: Gas flow and burner ignition are among the
first things that should be inspected.
Please See Page 58 for suggested items to inspect.
Installation Code and Annual Inspections:
The Vicinity of the Heater
Vehicles and Other
Objects
Reflector
Vent Pipe
Outside Air Inlet
Tubes
Gas Line
58 of 71
S
M
ERVICE
ANUAL
Do not store or use flammable objects, liquids or vapors near the heater.
Immediately remove these items if they are present.
See Page 6, Section 3.
Maintain the clearances to combustibles.
Do not hang anything from, or place anything on, the heater.
Make sure nothing is lodged underneath the reflector, in between the tubes or
in the decorative or protective grilles (included with select models).
Immediately remove objects in violation of the clearances to combustibles.
See Page 6, Section 3.
Support reflector with reflector hanger and support strap.
Reflector must not touch tube.
Make sure there is no dirt, sagging, cracking or distortion.
Do not operate if there is sagging, cracking or distortion.
Make sure reflectors are correctly overlapped. See Page 20, Section 6.5.1.
Clean outside surface with a damp cloth.
Venting must be intact. Using a flashlight, look for obstructions, cracks on the
pipe, gaps in the sealed areas or corrosion.
The area must be free of dirt and dust. Clean as required.
Remove any carbon deposits or scale using a wire brush.
See Page 31, Section 8.
Inlet must be intact. Look for obstructions, cracks on the pipe, gaps in the
sealed areas or corrosion.
The area must be free of dirt and dust. Clean and reinstall as required.
Make sure there are no cracks.
Make sure tubes are connected and suspended securely.
See Page 12, Section 6.
Make sure there is no sagging, bending or distortion.
Clean or replace as required.
Check for gas leaks. See Page 37 , Section 9.
All installation and service of ROBERTS GORDON
equipment must be performed by a contractor
qualified in the installation and service of equipment
sold and supplied by Roberts-Gordon LLC and
conform to all requirements set forth in the
ROBERTS GORDON
®
governmental authorities pertaining to the
installation, service and operation of the equipment.
To help facilitate optimum performance and safety,
Roberts-Gordon LLC recommends that a qualified
contractor conduct, at a minimum, annual
inspections of your ROBERTS GORDON
and perform service where necessary, using only
replacement parts sold and supplied by Roberts-
Gordon LLC.
manuals and all applicable
equipment
®
®

Advertisement

Table of Contents
loading

This manual is also suitable for:

Energytube em-80Energytube em-150Energytube em-200

Table of Contents