Assembly Instruction
DEGERtraker
Part II – Foundation and mast
Assembley foundation
2nd Step:
-
Insert mast mount centrally (height approx.10 cm).
-
Install bent bar-steel into the center of the foundation.
ATTENTION: Conduit must be inside the mast
-
Install bent bar-steel.
-
Install top layer of wire-mesh steel Q257A (cut into the formwork).
3th Step:
-
Create formwork for the receiving part.
-
Attach foundation formwork.
-
Affix foundation formwork in such a way that the formwork pressure generated by filling can be
absorbed.
-
Pour out and compact the foundation (without receiving part) using C20/30 concrete.
4th Step:
-
Affix mast with 2 reinforcement against rotation.
-
Insert mast into the foundation receiving part.
You do not have to take account of the
location of the bores in the flange.
ATTENTION: Conduit must be inside the mast until min.
10 cm above foundation top edge
-
Align mast vertically.
-
Fill up receiving part and mast base up to the top edge
of the foundation using grout concrete C25/30 (flowable)
and compact the concrete.
The concrete should be allowed to harden for at least 2 days before any further installation work is
done!
ATTENTION! Cable guide
We recommend you attach a junction box to the side of
the foundations, as shown in the adjacent drawing. The
cables from the junction box to the rotating head must be
designed as flexible rubber cables.
Assembly Instruction DEGERtraker 3000NT / 3000HD / 5000NT / 5000HD / 6000NT / 7000NT / 9000NT
Flexible
rubber cables
Junction box
2012-07-01
Page II-2
Use concrete backfill
from mast base to
foundation top edge
Conduit