Condensing
Boiler
100mm
22mmØ
plastic pipe
Condensing
Boiler
22mmØ condensate
drainage pipe, max external
length 3 metres
500mm min.
Diameter 100mm
min. plastic tube
Bottom of
tube sealed
Limestone
chippings
22 mm Ø plastic condensate
drainage pipe running
through the external wall
Condensing
10
CONDENSATE PIPEWORK
Visible air break
at plug hole
Sink with
integral
overflow
Insulation or
increase pipe size
Open end of
condensate drainage
pipe directly into gully
75 mm
below grating but
min.
above water level
75mm sink
waste trap
22mmØ
Soil & vent stack
minimum
450mm
and up to
3 storeys
Invert
Insulation or
increase pipe size
Condensate drainage pipe can be
run above or below ground
25mm
Drainage holes
Hole depth
400mm min.
by 300 Ø
Boiler
Insulation or
increase pipe size
43 mm 90°
M & F bend
CONDENSATE PIPEWORK
IMPORTANT:
CONDENSATE PIPEWORK:
•
•
•
•
External pipe work
Condensate soakaway
External rain water
pipe into foul water
Fitting an external air break
External
air break
Air gap
68 mm Ø PVC-u
strap on fitting
INSTALLATION & SERVICING INSTRUCTIONS
•
Ensure there are no
blockages in the pipe run
•
Care should be taken when
siting a soak-away to avoid
obstructing existing services
•
Condensate waste must not
be terminated into a septic
tank or cesspit
The condensate pipe must be a minimum of
22mm Ø plastic pipe.
The condensate pipework must fall at
least 50 mm per metre towards the outlet
and should take the shortest practicable
route.
The pipework must follow one of the options
shown opposite or discharge directly into a
vent stack min. 450mm above pipe invert or
into a gully below ground but above the water
level.
Wherever possible the condensate
discharge pipe work should be routed and
terminated internally. Should this not be
possible, and the only available route is
external, the following conditions should be
observed:
-
Pipe work length should be kept to a
minimum and the route as vertical as
possible.
-
Where pipe work is subjected to
extreme cold or wind chill, a weather
proof insulation should be used.
Alternatively the condensate pipework
could be increased to a minimum
diameter of 32mm without the
requirement to
insulate.he pipe run
The condensate drainage pipe may be run
above or below the ground to the soakaway.
The example shown opposite runs above
ground level.
The soakaway must use a 100mm diameter
plastic tube with two rows of three 12 mm
holes on 25 mm centres and 50 mm from
the bottom of the tube. The holes must face
away from the house.
The tube must be surrounded by at least
100 mm of limestone chippings to a depth
of 400mm.
Use the situation opposite when a rain water
down pipe is used to dispose of condensate
and the down pipe goes directly into an
existing sewer that carries both rainwater
and foul water.
An air break must be installed in the
32/43 mm pipework, between the boiler
condensate outlet and the drainpipe, outside
the property, to avoid flooding during
adverse weather conditions.