Natural Gas Capacity of Pipe
In Cubic Feet of Gas Per Hour (CFH)
Length of
Pipe in Feet
1/2"
10
132
20
92
30
73
40
63
50
56
60
50
70
46
80
43
90
40
100
38
(Pressure 0.5 psig or less and pressure drop of 0.3" W.C.; Based on
0.60 Specific Gravity Gas)
CFH = BTUH Furnace Input
Heating Value of Gas (BTU/Cubic Foot)
To connect the furnace to the building's gas piping, the installer
must supply a ground joint union, drip leg, manual shutoff valve,
and line and fittings to connect to gas valve. In some cases, the
installer may also need to supply a transition piece from 1/2" pipe
to a larger pipe size.
The following stipulations apply when connecting gas piping. Re-
fer to Gas Piping Connections figure for typical gas line connec-
tions to the furnace.
Gas piping must be supported external to the furnace cabinet
so that the weight of the gas line does not distort the burner
rack, manifold or gas valve.
Use black iron or steel pipe and fittings for building piping.
Where possible, use new pipe that is properly chamfered,
reamed, and free of burrs and chips. If old pipe is used, be
sure it is clean and free of rust, scale, burrs, chips, and old
pipe joint compound.
Use pipe joint compound on male threads ONLY. Always
use pipe joint compound (pipe dope) that is APPROVED
FOR ALL GASES. DO NOT apply compound to the first two
threads.
Nominal Black Pipe Size
3/4"
1"
1 1/4"
278
520
1050
190
350
730
152
285
590
130
245
500
115
215
440
105
195
400
96
180
370
90
170
350
84
160
320
79
150
305
Use ground joint unions.
Install a drip leg to trap dirt and moisture before it can enter
1 1/2"
the gas valve. The drip leg must be a minimum of three
1600
inches long.
1100
Install a 1/8" NPT pipe plug fitting, accessible for test gauge
980
connection, immediately upstream of the gas supply
760
670
connection to the furnace.
610
Always use a back-up wrench when making the connection
560
to the gas valve to keep it from turning. The orientation of
530
490
the gas valve on the manifold must be maintained as
460
shipped from the factory. Maximum torque for the gas valve
connection is 375 in-lbs; excessive over-tightening may
damage the gas valve.
Install a manual shutoff valve between the gas meter and
unit within six feet of the unit. If a union is installed, the
union must be downstream of the manual shutoff valve,
between the shutoff valve and the furnace.
Tighten all joints securely.
Connect the furnace to the building piping by one of the
following methods:
Rigid metallic pipe and fittings.
Semi-rigid metallic tubing and metallic fittings.
Aluminum alloy tubing must not be used in exterior
locations. In order to seal the grommet cabinet
penetration, rigid pipe must be used to reach the
outside of the cabinet. A semi-rigid connector to the
gas piping may be used from there.
Use listed gas appliance connectors in accordance with
their instructions. Connectors must be fully in the same
room as the furnace.
Protect connectors and semi-rigid tubing against physical
and thermal damage when installed. Ensure aluminum-
alloy tubing and connectors are coated to protect against
external corrosion when in contact with masonry, plaster, or
insulation, or subjected to repeated wetting by liquids such
as water (except rain water), detergents, or sewage.
29

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents