15. Commissioning Cont.
Turn the boiler OFF.
Open the gas valve outlet pressure test point
15 (fi gure 15.5) and connect the gauge.
Turn the boiler ON positioning the function se-
lector B in the position shown in fi gure 15.7
and ensure that the room thermostat is set to
"heat demand".
Figure 14.7
Loosen screws D and remove the service
panel (fi gure 15.9).
Figure 14.8
Watch the gauge and check to see if the ig-
nition pressure registerd corresponds to the
values given in the Technical Data. Turn off
the boiler and reignite it by turning the function
selector B to the 0 position and then back to
that indicated in fi gure 15.7.
Turn the boiler OFF.
Open the gas valve outlet pressure test point 15 (fi gure 15.5) and connect the gauge.
Turn the boiler ON positioning the function selector B in the position shown in fi gure 15.7 and ensure
that the room thermostat is set to "heat demand".
Loosen screws D and remove the service panel (fi gure 15.8).
To carry out the adjustment use the adjustment device (RISC) with the help of a screwdriver.
By rotating the device clockwise the pressure increases.
Adjust the gas pressure at the burner to the value according to the useful c.h. output wanted (Tab. 15.1).
Reassemble the service panel.
Close the gas valve outlet pressure test point 15 (fi gure 15.5).
Reassemble the front pannel of the case.
RIVA PLUS MANUAL

14.6 Checking the burner ignition:

B

14.7 Adjustment of the useful c.h. output:

Repeat this process two to three times leav-
ing 30 second intervals between each igni-
tion. Check the ignition pressures and visually
check that the burner lights uniformly and in a
controlled manner.
To carry out the adjustment move the function
selector 3 to the OFF position (Fig. 15.9) and
use the device (ACC).
Figure 14.9
Adjust the gas pressure at the injectors to the
value indicated in the tables of section 2. By
rotating the device clockwise the pressure in-
creases.
After the adjustment operations bring the se-
lector 3 of fi gure 15.9 back to the normal posi-
tion (ON).
Reassemble the service panel.
Close the gas valve outlet pressure test point
15 (fi gure 15.5).
Reassemble the front pannel of the case.
Important: after the checks all of the test
points must be sealed.