15. Commissioning Cont.
•
Turn the boiler OFF.
•
Open the gas valve outlet pressure test point
15 (fi gure 15.5) and connect the gauge.
•
Turn the boiler ON positioning the function se-
lector B in the position shown in fi gure 15.7
and ensure that the room thermostat is set to
"heat demand".
Figure 14.7
•
Loosen screws D and remove the service
panel (fi gure 15.9).
Figure 14.8
•
Watch the gauge and check to see if the ig-
nition pressure registerd corresponds to the
values given in the Technical Data. Turn off
the boiler and reignite it by turning the function
selector B to the 0 position and then back to
that indicated in fi gure 15.7.
•
Turn the boiler OFF.
•
Open the gas valve outlet pressure test point 15 (fi gure 15.5) and connect the gauge.
•
Turn the boiler ON positioning the function selector B in the position shown in fi gure 15.7 and ensure
that the room thermostat is set to "heat demand".
•
Loosen screws D and remove the service panel (fi gure 15.8).
•
To carry out the adjustment use the adjustment device (RISC) with the help of a screwdriver.
•
By rotating the device clockwise the pressure increases.
•
Adjust the gas pressure at the burner to the value according to the useful c.h. output wanted (Tab. 15.1).
•
Reassemble the service panel.
•
Close the gas valve outlet pressure test point 15 (fi gure 15.5).
•
Reassemble the front pannel of the case.
RIVA PLUS MANUAL
14.6 Checking the burner ignition:
B
14.7 Adjustment of the useful c.h. output:
•
Repeat this process two to three times leav-
ing 30 second intervals between each igni-
tion. Check the ignition pressures and visually
check that the burner lights uniformly and in a
controlled manner.
•
To carry out the adjustment move the function
selector 3 to the OFF position (Fig. 15.9) and
use the device (ACC).
Figure 14.9
•
Adjust the gas pressure at the injectors to the
value indicated in the tables of section 2. By
rotating the device clockwise the pressure in-
creases.
•
After the adjustment operations bring the se-
lector 3 of fi gure 15.9 back to the normal posi-
tion (ON).
•
Reassemble the service panel.
•
Close the gas valve outlet pressure test point
15 (fi gure 15.5).
•
Reassemble the front pannel of the case.
Important: after the checks all of the test
points must be sealed.
37