12-64B, 8-66B Installation, Operation and
Step 1.
Pre-Installation
A.
To get the best results, the sensor should be mounted 20 pipe diameters downstream from any flow disturbance
(valve, pipe elbow) and 10 pipe diameters upstream from any disturbance.
The instrument tag shows the model number, tag number (if
noted on the order) and serial number along with other
important safety information. Compare this information with the
appropriate pipe installation drawings to be sure the instrument
is the correct configuration. Match the tag serial number on the
enclosure, flow element and control circuit.
B.
Verify the serial numbers on the enclosures, flow element and electronics (control circuit) match. The instrument
may not work if the serial numbers do not match.
C.
Recommended installation/troubleshooting tools are a 1-3/8 inch open ended wrench to fit the NPT connection, a
small flat blade screw driver for manipulating potentiometers, a medium flat blade screwdriver for tightening
connections, 3 mm allen wrench for CENELEC approved instruments, and a DVM for Ohm/Voltage
measurements.
Step 2.
Flow Element Installation
Alert:
Install the flow element, with the Flat Up and Level (shown above) or parallel to the flow media (±2°) for top mounted
instruments. The enclosure, flow element and electronic control circuit card serial numbers should all match.

Troubleshooting Guide

On the top side of the local enclosure
Flow Element Serial Number.
Also Showing Sensor Orientation Flat.
(Located near the enclosure.
It is also on the enclosure tag.)
DO NOT change the orientation of the flow element in the enclosure as the interconnecting RTD and
heater wiring could be stressed and damaged. DO NOT apply any torque to the flow element
enclosure - only apply to the pipe surface itself.
Tag Location
Document 06EN003322 Rev. -
Electronics Serial Number

Advertisement

loading

Summary of Contents for FCI 12-64B

  • Page 1: Troubleshooting Guide

    24 Hour Factory Service Hot Line: 1 (800) 854-1993 12-64B, 8-66B Installation, Operation and Troubleshooting Guide Step 1. Pre-Installation To get the best results, the sensor should be mounted 20 pipe diameters downstream from any flow disturbance (valve, pipe elbow) and 10 pipe diameters upstream from any disturbance.
  • Page 2 When mounting the instrument the correct orientation of the flow element must be maintained to ensure repeatability to within specifications. Apply sealant to the male threads. Carefully place in the process media line with the machined flat facing up. Tighten the process connection. To avoid leaks do not overtighten or cross-thread connections. Shown below is the 1 inch NPT mounting.
  • Page 3 INSTALLATION, OPERATION AND TROUBLESHOOTING GUIDE Wiring the Instrument into the Customer’s Application: FCI recommends routing conduit to the enclosure. Below is a table to determine the wire size needed to route to the instrument. Connect the customer’s application (relays, lights, etc,.) to the terminal block switch points as required.
  • Page 4 8-66 Alarm Set Point Procedure Adjustment With The Sensing Element Wet 1. Determine that the sensing element is wet. 2. Apply power to the instrument and allow 10 minutes for the sensing element to become active and stabilize. 3. Locate the potentiometer (R5) and the red LED on the control circuit. (See the picture on the previous page.) 4.

This manual is also suitable for: