Relief Valve; Combustion Air Filter; Blower Compartment; Burner Maintenance - A.O. Smith VB-500, VB-750 Instruction Manual

Series 200/201 gas-fired copper boilers for hydronic heating and hot water supply
Hide thumbs Also See for VB-500, VB-750:
Table of Contents

Advertisement

Any safety devices including low water cutoffs used in conjunction
with this boiler should receive periodic (every six months)
inspection to assure proper operation. A low water cutoff device of
the float type should be flushed every six months. Periodic checks,
at least twice a year, should be made for water leaks.
More frequent inspections may be necessary depending on water
conditions.
The boiler-mounted gas and electrical controls have been
designed to give both dependable service and long life. However,
malfunction can occur, as with any piece of equipment. It
is therefore recommended that all components be checked
periodically by a qualified service agent for proper operation.

RELIEF VALVE

The safety relief valve should be opened at least twice a year
to check its working condition. This will aid in assuring proper
pressure relief protection. Lift the lever at the top of the valve
several times until the valve seats properly and operates freely.

COMBUSTION AIR FILTER

If the combustion air supply to the boiler contains dust, dirt, drywall
dust etc. a filter must be installed. An air filter is not supplied with
the boiler as shipped from the factory. The installer must provide a
filtering system in the air inlet to the boiler if dust, dirt or construction
dirt can be pulled into the boiler through the inlet air piping.
Periodically clean air filter per the manufacturer's instructions.

BLOWER COMPARTMENT

The blower compartment should be cleaned annually to remove
any dirt and lint that may have accumulated in the compartment
or on the blower and motor. Buildups of dirt and lint on the blower
and motor can create excessive loads on the motor resulting in
higher that normal operating temperatures and possible shortened
service life.

BURNER MAINTENANCE

Qualified servicers should follow this procedure when the boiler's
burner needs cleaning.
1. Turn off the electrical power to the boiler and close the main
manual gas shutoff valve(s). Allow the boiler parts to cool before
disassembly.
2. Loosen the flange and separate the gas train from the manifold
assembly.
3. Separate the burner from the blower adapter by first removing
the four (4) bolts and subsequently, the blower gas k ets. The
blower should be free to move at this point.
FOR DIRECT VENT UNITS: It is necessary to loosen and slide
the rubber coupling on the blower adaptor in order to move the
blower.
4. Loosen the seven bolts on the blower adapter at the base and
move the burner ground wire (Green) aside.
5. Lift the blower adapter and remove the manifold assembly up
from the 6 studs located on the cover plate and remove the
burner gasket.
6. Remove any loose foreign material such as dust or lint with
a vacuum. Check all ports for blockage. Dislodge any foreign
material causing blockage. Remove any soot or carbon deposits
with a rag making sure to remove any lint left on the burner by
vacuuming again.
7. Reverse the steps to reassemble the unit.
8. Restore electrical power and gas supply to the boiler.
• Put the boiler back in operation by following the Lighting and
Operating instructions in this manual.
• Check for gas leaks and proper boiler and vent operation.

CONDENSATE REMOVAL SYSTEM

Due to the highly efficient operation of this unit, condensate is
formed during operation and must be removed by the conden-
sate drain systems. Inspect the condensate drains and tubes
at least once a month and insure they will allow the free flow of
condensate at all times. The system must be inspected more
frequently in cold weather if the drain system is located in an
area, such as along the floor, where freezing tempera t ures are
likely to occur. The conden sate drain system must be protected
against freezing. Contact a qualified service agent to inspect
and correct the condition if freezing of the conden sate lines is a
problem. The unit is equipped with a blocked flue switch which
will shut the unit off if condensate is unable to drain and backs
up in the unit. A blocked flue error will appear when sufficient
condensate accumulates for this condition.
The transparent drain lines and condensate drain on the bottom
of the vent collector should be visually inspected at one month
intervals for blockage, particularly in the areas of the loops in the
lines which trap a small amount of conden sate, and the exit point
of the vent collector drain. Conden sate in portions of the line other
than the loop area indicates a blockage in the drain line. Flush the
46

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

200201Vw-500, vw-750Vw-1000Vf vb 1000Vf vb 750

Table of Contents