Software Licenses • It is prohibited to use data contained in firmware or software developed by SUNGROW, in part or in full, for commercial purposes by any means. • It is prohibited to perform reverse engineering, cracking, or any other operations that...
About This Manual This manual gives an introduction to the mounting, electrical connection and powering on/off of the Energy Storage System ("ESS"). Target Group This manual is intended for operators of the energy storage plant and qualified technical per- sons. The installation and operation must be performed only by qualified technical persons, who must: •...
Page 5
Indicates a slightly hazardous situation which, if not avoided, may result in minor or moderate injury. Indicates a potential hazard which, if not avoided, will result in device malfunction or property damage. Indicates supplementary information, emphasis on specific points, or tips related to the use of the product that might help to solve your problems or save your time.
Page 6
Sign Explanation Protective earthing (PE) terminal. This terminal should be connected for reliable grounding, to ensure the safety of the operator. Read the instructions before performing any operation on the product. Wear safety goggles.
Product Description Product Overview The electrical equipment, communication device, temperature control device, and fire sup- pression system of the ESS all adopt an integrated design. For electrical equipment, the LFP battery system is designed with a liquid cooling system, while the PCS adopts forced air cooling for heat dissipation.
1 Product Description Quick Installation Manual External Design 1.2.1 ESS External Design The external design of the ESS is shown in the figure below. figure 1-2 External Design *The figure is for reference only. The real product may differ. Name LED indicator Air inlet Emergency stop button...
Quick Installation Manual 1 Product Description The nameplate contains critical parameter information related to the ESS and should be protected against damages during transportation, installation, mainte- nance, overhaul, and other operations. Do not damage or remove the nameplate! LED Indicator The LED indicator is located at the top of the ESS cabinet.
1 Product Description Quick Installation Manual figure 1-3 Overall Dimensions figure 1-4 Dimensions of ESS with Its Door Fully Opened *The figure is for reference only and the real product may differ. 1.2.3 Ventilation Design The ESS has an air inlet at its front and an air outlet at its rear, as shown in the figure below.
Quick Installation Manual 1 Product Description figure 1-5 Air Inlet and Outlet *The figure is for reference only and the real product may differ. Internal Design 1.3.1 Internal Components The main electrical equipment inside the ESS cabinet are shown below. figure 1-6 Internal Structure of ESS Cabinet Name PCS (SC125CX)
1 Product Description Quick Installation Manual 1.3.2 PCS (SC125CX) PCS External Design The external design of the SC125CX Power Conversion System (PCS) is shown in the fig- ure below. figure 1-7 PCS External Design *The figure shown here is for reference only. The real product may differ. Description Name Locating pin...
Page 15
Quick Installation Manual 1 Product Description Description Name Fans are installed at the back of the cover plate, used Air inlet cover for forced cooling. Used to disconnect the equipment from the battery DC switch safely. * During product use, avoid DC positive/negative-to-ground short circuits and short circuits between positive and negative.
1 Product Description Quick Installation Manual 1.3.3 Power Distribution Box figure 1-8 External Design of Power Distribution Box figure 1-9 Operation Panel *The figure here is for reference only and the real product may differ. Description Name Used to restrict the free movement of the power distri- Locating pin bution box.
Quick Installation Manual 1 Product Description Description Name Used to bring circulating cool air into the power distribu- Air inlet tion box. Connection ports 4– Used for power supply or communication wiring of the 24Vdc device inside the cabinet. Communication port Used for the communication wiring of the equipment.
Page 18
1 Product Description Quick Installation Manual PACK The PACK (battery module) is mainly composed of cells connected in series. It is equipped with functions such as battery voltage and temperature sampling and balancing control. De- signed with chips dedicated to battery management, it receives control commands and up- loads the collected data over daisy chain communication.
Quick Installation Manual 1 Product Description table 1-6 RACK Data Rated Short-cir- DC output voltage Rated RACK Model voltage range power cuit current 691.2–934.4V 114kW 819.2V ≤20kA R0229BL-ACAA RACK Structure table 1-7 RACK Structure Arrangement Model ST225kWh-110kW-2h Note: indicates an 1P64S PACK (battery module). PCS stands for power con- version system, LCS for liquid cooling unit, and PMD for power distribution box.
Page 20
1 Product Description Quick Installation Manual figure 1-10 EMS300CP Web Homepage You can scan the QR code on the nameplate at the rear of the ESS cabinet to get the EMS300CP user manual, or scan this QR code directly: Remote Monitoring on iSolarCloud You can also monitor the ESS remotely via iSolarCloud.
If the product is equipped with an EMS300CP controller, ensure the gateway meter and electricity meter used with the EMS300CP have been installed before commissioning. In case of any problem or doubt, contact your transport service provider or SUNGROW in time.
• The foundation should be built in compliance with the foundation drawing provided, or approved, by SUNGROW. The tolerance for the upper surface of the foundation is ±5mm. • The foundation should provide sufficient and effective support for the equipment.
2 Mechanical Installation Quick Installation Manual • Build a cement foundation with sufficient cross-sectional area and height. The founda- tion height should be determined by the constructor based on the on-site geological conditions. • Take cable laying into consideration when building the foundation. In the process of foundation building, remove the muck immediately after exca- vation, to avoid affecting the hoist and transport of the equipment.
Page 25
Quick Installation Manual 2 Mechanical Installation Installation of One ESS figure 2-1 Space Required for One ESS Maintenance Space Requirements Item Maintenance tool- ing for non-PACK L1≥300mm, L2≥430mm, L3≥2500mm, L4=0 components PACK mainte- L1≥300mm, L2≥630mm, L3≥2000mm, L4≥400mm nance tooling...
Page 26
2 Mechanical Installation Quick Installation Manual Installation of Multiple ESSs figure 2-2 Space Required for ESSs in One Row Maintenance Space Requirements Item Maintenance tool- ing for non-PACK L1≥300mm, L2≥430mm, L3≥2500mm, L4=0 components PACK mainte- L1≥300mm, L2≥630mm, L3≥2000mm, L4≥400mm nance tooling...
Page 27
Quick Installation Manual 2 Mechanical Installation figure 2-3 Space Required for ESSs in Two Rows Maintenance Space Requirements Item Maintenance tool- ing for non-PACK L1≥600mm, L2≥430mm, L3≥2500mm components PACK mainte- L1≥600mm, L2≥630mm, L3≥2000mm nance tooling * The figure is for reference only. The product received may differ. When arranging the ESS cabinets in two rows, ensure that the two rows are aligned on both sides.
Installing the ESS outdoors is recommended, as per the general plant design standards. • For cabinets installed indoors due to layout constraints, SUNGROW specifies indoor arrangement requirements from the perspective of product design and maintenance only. The owner/EPC shall consider plant-level requirements in these cases.
Quick Installation Manual 2 Mechanical Installation figure 2-4 Handle with Forklift • Move the ESS using a forklift by the bottom forklift pockets. • Never insert the forklift forks into any position on the equipment else than the bottom pockets. The ESS will be delivered with forklift pockets exposed to air.
2 Mechanical Installation Quick Installation Manual • Make sure the connections of slings are all secure and reliable, and the length of the sling connected to each corner fitting is the same. • The sling length can be adjusted based on the actual situation on site. •...
Quick Installation Manual 2 Mechanical Installation figure 2-6 ESS Hoisting *The figure shown here is for reference only. The real product may differ. ESS Fixing After moving the ESS to the target position, fix it in place. You can fix the equipment by weld- ing or using L-shaped angle steels.
Page 32
2 Mechanical Installation Quick Installation Manual figure 2-7 L-shaped Angle Steels Installation Tools Tools that may be used when installing the L-shaped angle steels are as follows: Name Source Not included in the scope of supply Marker Not included in the scope of supply Hammer drill Angle steel Included in the scope of delivery...
Electrical Connection Precautions High voltage! Electric shock! • It is strictly forbidden to directly touch the live parts in the unprotected state! • Before installation, ensure that the all switches are off. Sand and moisture penetration may damage the electrical equipment in the system, or affect their operating performance! •...
Page 34
3 Electrical Connection Quick Installation Manual figure 3-1 Wiring Diagram table 3-1 Interface Description *Recommended cable specifications Name 3×95mm /copper wire AC output port 3×150mm /aluminum wire **EMS communication port 2×0.5mm shielded twisted-pair cable (connection port 2) LC communication port (con- 2×0.5mm shielded twisted-pair cable nection port 1)
Operations related to the electrical connection must only be performed by qualified electrical engineers, all in compliance with the “Safety Precautions” specified in this manual. SUNGROW shall not be held liable for any personal injury or property damage arising from failure to follow the safety instructions.
3 Electrical Connection Quick Installation Manual 3.3.2 Open Cabinet Door Open the cabinet door before wiring. figure 3-2 Open the Front Door Step Description Door locked Move the cover above the lock hole Insert the door key and turn it clockwise Rotate the handle clockwise to the position shown in the figure to open the front door 3.3.3 Prepare Cables...
• Select communication cables equipped with corresponding shielding protection features according to the requirements of SUNGROW. • Secure the power cables and the communication cables separately. Ensure a minimum space of 10cm between the lines of strong and weak electricity to avoid electromagnetic interference.
3 Electrical Connection Quick Installation Manual figure 3-3 Copper cable terminal connection sequence Name Name Copper bus bar Spring washer Copper connection Flat washer terminal Bolt Bolt fastening should be firm and reliable, and the exposed wire buckle should not be less than 2 buckles.
Quick Installation Manual 3 Electrical Connection Bolt fastening should be firm and reliable, and the exposed wire buckle should not be less than 2 buckles. 3.3.6 Cable Inlet Design Cables connecting the external devices to the ESS can be led through the cable inlet at the bottom of the ESS.
Page 40
3 Electrical Connection Quick Installation Manual Overview Grounding can be made in the following two ways: welding a grounding flat steel, or con- necting a grounding cable. For the location of the grounding point, see “ESS External Design”. 用户现场安装的设备(如无线路由器)需要就近接地。 Grounding Flat Steel (Recommended) Remove the protective tape from the grounding point and weld the hot-dip galvanized flat steel to the grounding point (the area where the flat steel and the ESS are joined together should be 40mm x 70mm).
Quick Installation Manual 3 Electrical Connection Carry out external ground connection in compliance with the actual on-site conditions and the instructions by the plant staff. Measure the ground resistance after completing the grounding. Make sure the resistance does not exceed 4Ω. The specific ground resistance should comply with the applicable national/local standards and regulations.
3 Electrical Connection Quick Installation Manual Step 3 Make sure the AC cables are connected properly in the correct positions. figure 3-7 AC Wiring Area Step 4 Strip the protective layer of the cables using wire strippers to expose the copper cores. Step 5 Crimp the OT terminal.
Page 43
Quick Installation Manual 3 Electrical Connection figure 3-8 Communication Ports table 3-2 Port Description Description Name NET1 Connected to PCS (the internal wiring has been completed) NET2 Used for inter-cabinet networking NET3 Used for inter-cabinet networking NET4 Reserved for 0.25C system networking...
3 Electrical Connection Quick Installation Manual • The system supports up to 10 ESS cabinets in parallel. The cabinet with an EMS is ac- cessed to the customer network and connected hand-in-hand with other cabinets that do not have EMS. •...
3 Electrical Connection Quick Installation Manual Port Point Usage CONN2-13/14 24V power supply for ATS CONN3-1/2, CONN3-3/4, EMS RS485 communication CONN3-5/6 CONN3-7/8 EMS dry contact input (DI1) CONN3-9/10 EMS DO output (DO1) CONN3 CONN3-11/12 FSS "flammable gas detector" dry contact output CONN3-13/14 Reserved...
Page 47
Quick Installation Manual 3 Electrical Connection • Moisture may get in if the product is not properly sealed. • Rodents may get in if the product is not properly sealed. Lock the cabinet door Step 1 Mount back the protective cover for the wiring area, by completing the steps for removal (see "Open Cabinet Door") in reverse.
The safety precautions in this manual do not cover all specifications to be fol- lowed, and all operations should be performed based on the site conditions. • SUNGROW shall not be liable for any loss arising from failure to follow the safety precautions in the manual. •...
Quick Installation Manual 4 Battery Connection • All connections must be carried out with distinctive guidance. Any guess and ambiguous attempts must be prohibited. • Key connections must be correct, reliable (without loosening) and in good contact, with- out short-circuits. •...
Page 50
4 Battery Connection Quick Installation Manual Step 2 Install the fuse. Open the cabinet door, and remove the sponge separators that hold the fuse plugs. figure 4-2 Position of Fuse Step 3 Insert the plugs that come with the fuse into the PACK bases properly. figure 4-3 Insert Fuse Plugs into PACK Bases When the aviation plug is connected in place, you will hear a "click".
Page 51
Quick Installation Manual 4 Battery Connection Step 4 Connect the power cables between the PCAKs. The positive connector of the power cable between the PACKs has been secured on the RACK, and the negative connector is secured on the side bracket with the quick-connect clip and cable tie. When the aviation plug is connected in place, you will hear a "click".
Page 52
4 Battery Connection Quick Installation Manual Step 5 Connect the power cable between the PACK and the PCS: Connect the BAT+ of Pack1# to the BAT+ of PCS; Connect the BAT- of Pack4# to the BAT- of PCS. figure 4-5 PACK Wiring Diagram When the aviation plug is connected in place, you will hear a "click".
Powering up and Shutdown Powering up • The equipment can only be put into operation after confirmation by a professio- nal and approval of the local energy department. • For equipment that has a long shutdown time, inspect it thoroughly and care- fully and make sure all the indicators meet the relevant requirements before powering up.
Page 54
5 Powering up and Shutdown Quick Installation Manual Step 1 PCS: Set the DC-side load switch of the PCS to "ON". Make sure the emergency stop button on the cabinet is in the reset state. Step 2 Turn on the QF1 (main AC switch) on the panel to power the AC side of the system. Step 3 Turn on the Q1 (auxiliary AC switch) on the panel to power on the auxiliary power supply.
Quick Installation Manual 5 Powering up and Shutdown Shutdown 5.2.1 Planned Shutdown Planned shutdown refers to an interruption to the equipment operation that is scheduled in advance for overhaul, test, or maintenance. Shut the system down via the control software, and switch off the battery relay (in case of an emergency, you can press the emergency stop button on the cabinet).
Document QR Code LC300 User Manual If the problem persists or there are any other questions, please contact SUNGROW. It would be helpful if you could provide the below information: • Model and S/N of the ESS and its internal device;...
Appendix Abbreviations Abbreviation Definition Battery Module (or PACK) Battery Cluster (or RACK) Battery Management Unit BCMU (CMU) Battery Cluster Management Unit (CMU for short) BSMU (SMU) Battery System Management Unit (SMU for short) Battery Management System Battery System Controller Battery Collection Panel. Battery DC inputs are combined into the BCP DC copper bar, and connected to the PCS DC side through the copper bar on the other side of the BCP.
7 Appendix Quick Installation Manual Technical Data ST225kWh-110kW-2h Product Model Battery Side Cell Type System Battery Configuration 256S1P Rated Battery Capacity 229kWh Battery Voltage Range 691.2V–934.4V PCS Side Rated Output Power 110kW ≤3% (at rated power) Total Harmonic Distortion (THD) ≤0.5% (at rated power) DC Component Rated Grid Voltage...
• The customer shall give SUNGROW a reasonable period to repair the faulty device. Exclusion of Liability In the following circumstances, SUNGROW has the right to refuse to honor the quality guarantee: • The free warranty period for the whole machine/components has expired.
The fault or damage is caused by installation, repairs, modification, or disassembly per- formed by a service provider or personnel not from SUNGROW. • The fault or damage is caused by the use of non-standard or non-SUNGROW compo- nents or software. •...
Page 61
Sungrow Power Supply Co., Ltd. www.sungrowpower.com...