Download Print this page
SolarEdge Home Battery Connection And Configuration
SolarEdge Home Battery Connection And Configuration

SolarEdge Home Battery Connection And Configuration

For australia
Hide thumbs Also See for Home Battery:

Advertisement

Quick Links

SolarEdge Battery Connection and Configuration Guide
for Australia
Revision History
Version 6.2, February 2025: Updated oversizing definitions
Version 6.1, September 2024: Reformatted
Version 6.0, May 2024: Added 3Ph Residential Booster (AUB) Inverter and 3Ph SLD's
Contents
Overview ..................................................................................................................................................................................... 2
Connect battery communication and DC ....................................................................................................................... 2
Single Phase Home Hub Inverter ................................................................................................................................ 2
Three Phase Booster (AUB) Inverter ........................................................................................................................... 4
Connect DC Combiner cables .............................................................................................................................................. 4
Connect when the DC Combiner is not used .................................................................................................................... 5
Pre-startup battery polarity check..................................................................................................................................... 6
Battery association .................................................................................................................................................................. 6
Run a battery self-test............................................................................................................................................................ 7
Connect backup interface communication cables ...................................................................................................... 7
Single Phase Home Hub Inverter ................................................................................................................................ 8
Current Transformer (CT) installation ............................................................................................................................... 9
Export/import energy metering in a single-phase grid installation ............................................................... 9
Home Hub 3Ph metering voltage connections ......................................................................................................... 10
Meter connections for multiple Home Hub inverter sites .................................................................................... 10
Set backup interface CT value .......................................................................................................................................... 10
Enable backup applications .............................................................................................................................................. 11
Backup power applications ......................................................................................................................................... 11
Three phase booster (AUB) inverter metering connections ................................................................................. 11
Modbus meter interface .............................................................................................................................................. 12
Modbus meter installation: ......................................................................................................................................... 13
Inline meter interface .................................................................................................................................................. 15
Inline meter installation ............................................................................................................................................. 16
System Startup and Shutdown ........................................................................................................................................ 17
Common Installation Configurations ............................................................................................................................ 18
New label requirements .............................................................................................................................................. 46
Guidance related to PV DC oversizing of SolarEdge systems........................................................................ 46
Guidance related to RCD requirements ................................................................................................................ 48
PV System residual current factors ........................................................................................................................ 48
Residual Current Device (RCD) ................................................................................................................................ 48
Installation and selection of an external RCD device ..................................................................................... 48
SolarEdge Solution Connection and Configuration Guide for Australia
Version 6.2, February 2025
1

Advertisement

loading
Need help?

Need help?

Do you have a question about the Home Battery and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for SolarEdge Home Battery

  • Page 1: Table Of Contents

    New label requirements .............................. 46 Guidance related to PV DC oversizing of SolarEdge systems................ 46 Guidance related to kWp ratio for STC calculations – SolarEdge Home Battery ......... 47 Guidance related to RCD requirements ........................ 48 PV System residual current factors ........................48 Residual Current Device (RCD) ..........................
  • Page 2: Overview

    3Ph Booster (AUB) inverter, the RS485 connection is not possible, but on the SolarEdge Home Network it can be used. If x3 batteries are installed on a single inverter, the DC Combiner or SolarEdge Branch Connectors can be used. Use the following cable types: DC - 6mm - 10mm CSA 600V insulated depending on route length.
  • Page 3 6. If 2 or more batteries are being connected, daisy chain the connections between each battery. 7. Close Communication Gland 2 with a torque of 5 N·m. NOTE When connecting the SolarEdge Home Battery to an HD Wave or Genesis, the EN line connection is not required. SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 4: Three Phase Booster (Aub) Inverter

    4. Proceed with the battery installation, as described in the battery installation guide. Connect DC Combiner cables For the installation of three SolarEdge Home Batteries, the DC Combiner can be utilized. Up to three SolarEdge Home Battery installations can be managed via the SolarEdge Branch Connectors instead. Use the following cable types: DC - 6mm - 10mm CSA 600V insulated depending on route length.
  • Page 5: Connect When The Dc Combiner Is Not Used

    DCD connection unit. When two or three SolarEdge Home Batteries are installed, use branch connectors. The inverter's DCD connection unit has one input and two DC connections, one from the Power Optimizers and one from the batteries.
  • Page 6: Pre-Startup Battery Polarity Check

    6. Repeat for all batteries connected. Battery association The 'Association' stage is only required for battery connection via the SolarEdge Home Network' protocol, when running through the battery commissioning stages. For batteries, connection via RS- 485 the Association stage is not required.
  • Page 7: Run A Battery Self-Test

    Connect backup interface communication cables To set up the Backup Interface for backup operation (on the Single-Phase Home Hub Inverter), a communication connection between the Backup Interface and the inverter is required. SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 8: Single Phase Home Hub Inverter

    7. Remove the connector from the port labelled Backup Interface on the communication board. 8. Connect the RS485 communication cable to the connector, as displayed below. 9. Connect the 12V power supply connection to the connector, as displayed below. SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 9: Current Transformer (Ct) Installation

    Do not use the method of twisting the wires and taping them together. This type of connection is not reliable, and the wires may eventually disconnect from each other. SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 10: Home Hub 3Ph Metering Voltage Connections

    The default CT setting for the meter within the Home Hub is 70A. The CT value for the device within the Backup Interface is 100A and the default setting needs to be updated. SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 11: Enable Backup Applications

    Three phase booster (AUB) inverter metering connections When metering a 3Ph site SolarEdge offers two metering options, one being via the Mobus meter, the second via the Inline meter. SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 12: Modbus Meter Interface

    Modbus address of the meter. The addressing options are listed in the table below. Termination DIP switches- (TERM 1, 2): used to set RS485 termination. termination options are listed in the table below. SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 13: Modbus Meter Installation

    CTs can be opened for installation around a conductor. A nylon cable tie may be secured around the CT to prevent accidental opening. 6. Install the CTs with the arrows pointing to the grid for consumption or export measurement. SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 14 5. Connect the meter's RS485 G, A+, and B- connectors to the G, A, and B connecters in the inverter. If the SolarEdge device is at the end of the RS485 bus, terminate as follows: 1. Inverter - Terminate by switching a termination DIP-switch inside the inverter to ON (top position).
  • Page 15: Inline Meter Interface

    RS485 - a detachable connector for wired connectivity with the inverter. Three push buttons - to operate the inline meter display. LEDs - used to monitor meter status: Orange: meter operation • Blue: SolarEdge Home Network/RS485 communication status • SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 16: Inline Meter Installation

    2. Using one of the below wiring schemes, connect the AC wiring to the terminal blocks at the top and the bottom of the inline meter. The following image displays Import and Export Metering: The following image displays Consumption Metering: SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 17: System Startup And Shutdown

    To shut down the system: 1. Move the SolarEdge inverter toggle to the OFF position and wait until the green LED is blinking, indicating that the DC voltage is safe (<50V), or wait five minutes before continuing to the next step.
  • Page 18: Common Installation Configurations

    Version 6.2, February 2025 Common Installation Configurations Figure 1: Home Hub, Backup Interface, SolarEdge Home Battery, Full Home Backup SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 19 Version 6.2, February 2025 Figure 2: Home Hub, Backup Interface, Dual SolarEdge Home Batteries, Full Home Backup SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 20 Version 6.2, February 2025 Figure 3: Home Hub, Backup Interface, Three SolarEdge Home Batteries, DC Combiner, Full Home Backup, Option A SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 21 Version 6.2, February 2025 Figure 4: Twin Home Hub, Backup Interface, Three SolarEdge Home Batteries, Full Home Backup, Option A SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 22 Version 6.2, February 2025 Figure 5: Twin Home Hub, Backup Interface, Three SolarEdge Home Batteries, DC Combiner, Full Home Backup, Option B SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 23 Version 6.2, February 2025 Figure 6: Three Home Hub, Backup Interface, Three SolarEdge Home Batteries, Full Home Backup, Option A SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 24 Version 6.2, February 2025 Figure 7: Three Home Hub, Backup Interface, Three SolarEdge Home Batteries, DC Combiner, Full Home Backup, Option B SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 25 Version 6.2, February 2025 Figure 8: Three Home Hub, Backup Interface, Three SolarEdge Home Batteries, Full Home Backup, Option C SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 26 Version 6.2, February 2025 Figure 9: Home Hub, Backup Interface, and SolarEdge Home Battery, Partial Home Backup SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 27 Version 6.2, February 2025 Figure 10: Home Hub, Backup Interface, Dual SolarEdge Home Batteries, Partial Home Backup SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 28 Version 6.2, February 2025 Figure 11: Home Hub, Backup Interface, Three SolarEdge Home Batteries, DC Combiner, Partial Home Backup SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 29 Version 6.2, February 2025 Figure 12: Home Hub, Backup Interface, Dual SolarEdge Home Batteries, Partial Home Backup and AC Coupled Inverter SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 30 Version 6.2, February 2025 Figure 13: Home Hub, Backup Interface, Three SolarEdge Home Batteries, DC Combiner, Partial Home Backup and AC Coupled Inverter SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 31 Version 6.2, February 2025 Figure 14: Home Hub, Backup Interface, Dual SolarEdge Home Batteries, Partial Home Backup, 3Ph Grid SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 32 Version 6.2, February 2025 Figure 15: Home Hub, Backup Interface, Three SolarEdge Home Batteries, DC Combiner and Partial Home Backup, 3Ph Grid SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 33 Version 6.2, February 2025 Figure 16: Home Hub, Backup Interface, Dual SolarEdge Home Batteries, Partial Home Backup, 3Ph Grid and AC Coupled Inverter SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 34 Version 6.2, February 2025 Figure 17: Home Hub, Backup Interface, Three SolarEdge Home Batteries, DC Combiner and Partial Home Backup, 3Ph Grid and AC Coupled Inverter SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 35 Version 6.2, February 2025 Figure 18: Home Hub, SolarEdge Home Battery additon to site with HD Wave, 1Ph Grid, metering option 1 – Existing CT SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 36 Version 6.2, February 2025 Figure 19: Home Hub, SolarEdge Home Battery additon to site with HD Wave, 1Ph Grid, metering option 2 – Existing metering SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 37 Version 6.2, February 2025 Figure 20: Home Hub, Backup Interface, SolarEdge Home Battery additon to site with HD Wave,1Ph Grid, metering option 1 – Existing CT SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 38 Version 6.2, February 2025 Figure 21: Home Hub, Backup Interface, SolarEdge Home Battery additon to site with HD Wave,1Ph Grid, metering option 2 – Existing Metering SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 39 Version 6.2, February 2025 Figure 22: Three Home Hub's, x6 SolarEdge Home Batteries, 3Ph metering in the existing switch board. SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 40 Version 6.2, February 2025 Figure 23: Three Home Hub's, x6 SolarEdge Home Batteries, 3Ph metering in existing switch board, partial backup on one phase only. SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 41 Version 6.2, February 2025 Figure 24: Home Hub, SolarEdge Home Battery Partial Backup, StorEdge, LG RESU Prime, Metering Option A. SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 42 Version 6.2, February 2025 Figure 25: Home Hub, SolarEdge Home Battery, Partial Backup, StorEdge, LG RESU Prime, Metering Option B. NOTE The Home Hub and StorEdge inverters are separate systems (No Leader Follower configuration). Both systems require their own individual site IDs as they cannot be combined in the Monitoring platform.
  • Page 43 Version 6.2, February 2025 Figure 26: Home Hub, SolarEdge Home Battery, Full Homel Backup, Genesis, SESTI S4 , LG RESU Prime, Metering via Backup Interface. SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 44 Version 6.2, February 2025 Figure 27: 3Ph Inverter (PV Connected) x3 Genesis inverters each with Dual Home Battteries, Metering via Modbus Meter. SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 45 Version 6.2, February 2025 Figure 28: 3Ph Booster Inverter (PV Connected) Home Batttery via Home Netwrok, Metering via Modbus Meter. SolarEdge Solution Connection and Configuration Guide for Australia...
  • Page 46: New Label Requirements

    Table 1: Definitions and corresponding Product Code suffix designations. Guidance related to PV DC oversizing of SolarEdge systems To SolarEdge inverters provide the ability to significantly oversize the system's PV array once a battery is connected to facilitate improved battery charging performance.
  • Page 47: Guidance Related To Kwp Ratio For Stc Calculations - Solaredge Home Battery

    Version 6.2, February 2025 Figure 28: Home Hub SE5000H-MM maximum oversizing example Guidance related to kWp ratio for STC calculations – SolarEdge Home Battery The applicable volume of STC's is defined by the inverter type and its definition. Home Hub as a multiple mode inverter that allows greater PV DC oversizing than the non-multiple mode inverters such as the Genesis inverter.
  • Page 48: Guidance Related To Rcd Requirements

    PV array, cables or inverter (DC). The RCD in the SolarEdge inverter can detect leakage on the DC side. There are 2 trip thresholds for the RCD as required by the DIN VDE 0126-1-1 standard. A low threshold is used to protect against rapid changes in leakage typical of direct contact by people.
  • Page 49 Installation and selection of an external RCD device Installation of an RCD must always be conducted in accordance with local electrical regulations and standards. SolarEdge recommends the use of a type-A RCD. Unless a lower value is required by the specific local electric regulations.

This manual is also suitable for:

Home hub inverter