Cama HANDI-LIFT EA9 Installation Manual

Hide thumbs Also See for HANDI-LIFT EA9:

Advertisement

Quick Links

Handi-lift EA9
INSTALLATION MANUAL
FOR HANDI-LIFT EA9
Original Version
© 2022
Side 1 af 28
Version 1.0

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the HANDI-LIFT EA9 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Cama HANDI-LIFT EA9

  • Page 1 Handi-lift EA9 INSTALLATION MANUAL FOR HANDI-LIFT EA9 Original Version © 2022 Side 1 af 28 Version 1.0...
  • Page 2: Table Of Contents

    Handi-lift EA9 Table of contents Introduction....................3 1.1 Check the part and drawing ................3 1.2 Electrical installation ..................3 Forces on the building .................. 4 Install the rails .................... 5 3.1 Column installation ..................5 3.2 Upper and lower installation ................5 Installing the lift unit .................
  • Page 3: Introduction

    Handi-lift EA9 1 Introduction 1.1 Check the part and drawing Before you start installing, please read this installation manual. Check the received parts for transport damage. Next, study carefully the installation drawing that comes with the lift to ensure that all angels and dimensions are correct, and all dimensions are there.
  • Page 4: Forces On The Building

    Handi-lift EA9 2 Forces on the building Wall Mounted Rail 1. For 300 kg lifts the top (Main) rail fixings are M10x90mm (Class 4.6) coach screws + plugs, 2 pieces in each end, and the rest is glue bolts M10x90 (Class 8.8) If the lift is 225 kg all rail fixings are M10x90mm (Class 4.6) coach screws...
  • Page 5: Install The Rails

    Handi-lift EA9 3 Install the rails 3.1 Column installation If the Handi-Lift is installed on columns, you need to start with them. Place the columns after the measurements on the drawing they are usually numbered with the lowest number at the foot of the stairs.
  • Page 6 Handi-lift EA9 Note! Measurement C is the upper edge of the inner profile. Make a line through mark A-A and D. And make a line through mark C-C. fig. 1 fig. 2 fig. 1 © 2022 Side 6 af 28...
  • Page 7 Handi-lift EA9 Place the upper rail on the wall or columns and fasten it in each end, on a wall installation drill Ø12 mm holes in the wall for glue bolts. Minimum 90mm into the wall. On an installation on columns drill Ø8,5mm holes and make a M10...
  • Page 8 Handi-lift EA9 Fasten the rail with 2 coach screws at top and bottom, while you drill and glue the rest, see fig Make sure that the holes are nice and clean. Make sure that all measurements are correct. fig. 5 Fill the holes with glue and insert the M10 threaded rod in the hole.
  • Page 9 Handi-lift EA9 In order to protect the floor, it is an advantage to put cardboard underneath the rail. fig. 10 First you will have to remove the screws and then you can remove the limit switch, so you are able to drive the lift on the rail at the bottom fig.
  • Page 10 Handi-lift EA9 Remove the aluminum cover from the support rail fig. 12 Install and tighten the steel part of the support rail fig. 13 Tape can be added to protect the rail when sliding it into the lift fig. 14 ©...
  • Page 11: Installing The Lift Unit

    Handi-lift EA9 4 Installing the lift unit 4.1 Place the lift unit on the rail You are now ready to start installing the lift on the rail. fig. 15 fig. 16 Open the platform manually (fig. 15) so you can install the temporary power (fig.
  • Page 12 Handi-lift EA9 Insert the Installers remote control fig. 17 Close the platform again manually fig. 18 Reinstall the aluminum cover on the support rail fig. 19 © 2022 Side 12 af 28 Version 1.0...
  • Page 13 Handi-lift EA9 Slide the rail into the lift fig. 20 fig 20 © 2022 Side 13 af 28 Version 1.0...
  • Page 14 Handi-lift EA9 Fasten the rail above the lift fig. 21 Use installers remote to drive the lift up the rail, so you can fasten the lower part of the rail. Guide the chain into the rail fig. 22 Now install the screws you took out earlier.
  • Page 15 Handi-lift EA9 fig. 24 fig. 25 Install the cable cover so you can slide the 7x1 main cable into the rail all the way to the top and vice versa if the power is at the bottom. fig. 26 © 2022 Side 15 af 28 Version 1.0...
  • Page 16 Handi-lift EA9 fig. 27 fig. 27 Mark up where the holder for the energy chain needs to be installed. Install it. fig. 27 © 2022 Side 16 af 28 Version 1.0...
  • Page 17 Handi-lift EA9 fig. 28 fig. 28 Make sure the platform is in level at the top landing Adjust the platform if not in level fig. 29 © 2022 Side 17 af 28 Version 1.0...
  • Page 18 Handi-lift EA9 Adjust the barrier arm at both bottom and top position. Make sure both arms are adjusted, so they are vertical and parallel. The photo shows the bottom position. fig. 30 Adjust the barrier arms in horizontal position. Make sure both arms are adjusted, so they are both horizontal and parallel.
  • Page 19: Connect The Electrical

    Handi-lift EA9 4.2 Connect the electrical Now it is time to install the control boxes. Please note whether your lift comes with wired controls or battery controls. Battery controls: The wires are connected to the safety cut-out as follows: L1 is connected to terminal 2...
  • Page 20: Load Cell Adjustment

    Handi-lift EA9 4.2.1 Load cell adjustment Test the lift with maximum load (e.g. 225kg.) + 50kg. The load cell is adjusted from the factory, however if it is necessary to adjust it, it is done by turning the load cell sensor. This is installed at the upper cross bar on the platform, right next to where the wiring from the platform comes up.
  • Page 21: Raise/Lower Unit

    Handi-lift EA9 The completed installation fig. 32 5 Raise/lower unit The raise/lower unit is adjusted from the factory, if adjustment is needed then you can do as follows: The bolt is moved up/down as needed. Make sure there is 1½-2 mm space between the bolt and the inductive sensor.
  • Page 22 Handi-lift EA9 Adjust the raise/lower unit at the top as described for the bottom fig. 34 - top © 2022 Side 22 af 28 Version 1.0...
  • Page 23: Installation Test Certificate

    Rated load: _________ kg Stairlift serial no: _________________ Rated speed: ________ m/s Type and year of manufacturer: ___________________ Manufacturer: CAMA Lift ApS, Ellehammervej 6, DK-9900 Frederikshavn Contract electrical supply: _________ V _________ Phase _________ Hz Mains supply fuse rating: _________ A √...
  • Page 24 Handi-lift EA9 Verify that the mechanism for emergency/manual operates correctly The alarm device when activated operates correctly All notices, etc. are correctly displayed m. Undergo without failure a dynamic test to check the forces imposed by the maximum working load...
  • Page 25: Appendix 1 - Installation On Brackets

    Handi-lift EA9 7 Appendix 1 – installation on brackets In cases where the wall is uneven or if there is an obstacle, you can use wall brackets to solve the problem. Below you will find a guide on how to...
  • Page 26 Handi-lift EA9 Clean the holes for dust and debris fig. 37 Fill the holes with glue fig. 38 Insert the bracket fig. 39 © 2022 Side 26 af 28 Version 1.0...
  • Page 27 Handi-lift EA9 Hang the rail on the brackets and fasten it temporarily Drill 5 mm holes through both rail and brackets fig. 40 Take down the rail and drill 10,5 mm holes in the rail fig. 41 Drill holes or thread in the brackets fig.
  • Page 28 Handi-lift EA9 Make sure the distance to the main rail is correct fig. 43 Hang the support rail on the brackets fig. 44 © 2022 Side 28 af 28 Version 1.0...

Table of Contents