Page 3
ES100 II ESS Unit User Manual WARNING: HIGH VOLTAGE IN SIDE CAUTION: THE DC FUSE MUST HAVE BEEN TURNED OFF BEFORE SERVICING MADE IN CHINA...
Page 4
ES100 II ESS Unit user manual Statement of Law Copyright of this document belongs to TBB Renewable (Xiamen) Co., Ltd. No part of this documentation maybe excerpted, reproduced, translated, annotated or duplicated in any form or by any means without the prior written permission of TBB Renewable (Xiamen) Co., Ltd. All Rights Reserved.
Page 5
Preface Manual declaration The ES100 II lithium iron phosphate battery can be widely applied to energy storage systems including backup power, solar off grid, solar energy storage, solar hybrid, PV power generation, etc. This user manual details its basic structure, parameters, basic procedures and ways of installation...
Page 6
ES100 II ESS Unit user manual Contents B4850 ESS Unit User Manual 1. Introduction ............................1 1.1 Brief Introduction ........................1 1.2 Product Properties ........................1 1.3 Product identity definition ....................... 2 2. Product Specification ........................3 2.1 Size and Weight ........................3 2.2 Performance Parameter ......................4...
Page 7
ES100 II lithium iron phosphate battery system is a standard battery system unit. Customers can choose a certain number of ES100 II according to their needs, to form a larger capacity battery storage through parallel connection, to meet the user's long-term power supply needs. The product is especially suitable for applications with high operating temperatures and limited installation space, requiring long power backup time and long service life.
Page 8
ES100 II ESS Unit user manual 1.3 Product identity definition B4850 ESS Unit User Manual Figure 1-1 Battery Energy Storage System nameplate Battery voltage is higher than safe voltage, direct contact with electric shock hazard. Be careful with your actions and be aware of the dangers.
Page 9
ES100 II ESS Unit user manual 2. Product Specification 2.1 Size and Weight Table 2-1 ES100 II Device size Nominal Nominal Product Dimension Weight Voltage Capacity ES100 II DC48V 105Ah 482.6×450×133.4mm 40kg...
Page 10
Final discharge voltage(V) Cycle Life 90% DoD,6000 cycles life Charging temperature range 0℃~+55℃ Discharging temperature range -20℃~+55℃ -20℃~+45℃ 1month Storage temperature 0℃~+35℃ 3months 2.2.1 Front Panel Interface Definition 3 4 5 6 7 Figure 2-2 The interface of ES100 II...
Page 11
ES100 II ESS Unit user manual Table 2-3 Interface Definition Item Name Definition Connect to battery positive output cable or positive Positive socket parallel cable OFF/ON button, must be on the "ON" state when in use Power switch The number of green lights on shows the remaining battery power.
Page 12
Table 2-6 defines the pins of each interface. ES100 II is designed with 3 RJ45 ports. The CAN/RS485 port is used for CAN or RS485 communication with the inverter, and the PARALLEL PORTS IN and OUT are used for parallel communication with the battery bank.
Page 13
ES100 II ESS Unit user manual Table 2-6 Port Description Note PIN4: CANH For communication with inverters PIN5: CANL PIN3: 485-1A CAN/RS485 For communication with inverters or an upper computer PIN6: 485-1B PIN1、2、7、8:NC PIN4:485-2A For parallel communication PIN5:485-2B PARALLEL PORTS PIN3:DI+...
Page 14
ES100 II ESS Unit user manual 2.2.4 LED Explanations System Status Battery SoC LED Shutdown Hibernate All OFF Normal Flash 1 Indicate based on the battery SoC Alarm Flash 3 Flash 3 Standby Slave module address Flash 1 Flash 4...
Page 15
ES100 II ESS Unit user manual Table 2-7 SoC light display and corresponding battery capacity Status Charging Discharging Capacity indicator 0~25% Flashing 25~50% Flashing 50~75% Flashing 75~100% Flashing Running indicator Flashing 2.3 Battery Management System (BMS) 2.3.1 Voltage Protection Low Voltage Protection during Discharging Process:...
Page 16
ES100 II ESS Unit user manual 2.3.3 Temperature Protection Less/Over Temperature Protection during Charging Process: When battery’s temperature is beyond range of 0℃ ~+55℃ during charging, the temperature protection will start, and the device will stop the charging process. Less/Over Temperature Protection during Discharging Process:...
Page 17
ES100 II ESS Unit user manual 3. Installation and Configuration 3.1 Ready for installation Safety Requirement This system can only be installed by personnel who have been trained on the power supply system and have sufficient knowledge of the power system.
Page 18
ES100 II ESS Unit user manual 3.1.2 Tools and data Hardware tool Tools and meters that may be used are shown in table 3-1. Table 3-1 Tool instrument Name Screwdriver (word, cross) AVO meter Wrench Clamp meter Inclined pliers Insulating tape...
Page 19
ES100 II ESS Unit user manual 3.1.4 Unpacking inspection When the equipment arrives at the installation site, loading and unloading should be carried out according to the rules and regulations, to prevent it from being exposed to sun and rain.
Page 20
ES100 II ESS Unit user manual User Manual User manual Crown Screws Screw M6*19 3.1.5 Engineering coordination Attention should be paid to the following items before construction: Power cable specification. The power cable specification shall meet the requirements of maximum discharge current for each product.
Page 21
ES100 II ESS Unit user manual 3.2 Equipment installation Table 3-3 Installation steps Confirm that the ON/OFF switch on the front panel Installation Step1 of battery is in the “OFF” state to ensure no live preparation operation. 1. Cabinet placement position determination...
Page 22
ES100 II ESS Unit user manual 3.2.2 Mechanical installation Installation method 1: With Cabinet installation 1. Place the battery cell on the cabinet bracket as shown in the figure and push it into the installation position of the cabinet. (The cabinet structure in the figure is for reference only) Figure 3-2 2.
Page 23
ES100 II ESS Unit user manual 3. Place another bracket in the rear of the battery and push it to the buckle position. Figure 3-6 4. Stack the required number of battery and bracket combinations as described above, and fasten the upper and lower buckles.
Page 24
ES100 II ESS Unit user manual 4. Use,maintenance and troubleshooting 4.1 Battery system usage and operation instructions After completing the electrical connection, please follow these steps to start the battery system. 1. Refer to 2.3.2 for the definition of the DIP switch and prepare for the DIP before turning on the system, and then turn the switch ON/OFF to ON.
Page 25
ES100 II ESS Unit user manual Table4-2 a) The battery's long-term continuous charging current should be ≤0.5C Charging b) If the battery capacity is empty, please charge it within 48 hours after the battery is empty. Equipment c)The long-term continuous discharge current of the battery should be ≤1C...
Page 26
ES100 II ESS Unit user manual 4.3 Analysis and treatment of common faults Analysis and treatment of common faults in the Table 4-4: Table 4-4 Analysis and treatment of common faults Fault phenomenon Reason analysis Solution The indicator does not...