  • Page 1 FHDQ135 Floor Stand Assembly SOP July/17/24 Rev.4...
  • Page 2 FHDQ135 Floor Stand Parts List...
  • Page 3 FHDQ135 Floor Stand Parts List (1/4) Item Parts Name Image Quantity Note Provides the vertical structure to mount the • 2 PCS Vertical column module main beams and provides rollers for the stand. Arrow mark Provides a horizontal structure between the 2 •...
  • Page 4 FHDQ135 Floor Stand Parts List (2/4) Item Parts Name Image Quantity Note Arrow mark Provides an extension of the main beams on • the right side. Right wing beam 2 PCS When assembling this part, its arrow mark • must face the top side.
  • Page 5 FHDQ135 Floor Stand Parts List (3/4) Item Parts Name Image Quantity Note Attaches vertical column to main beams and • M4x10 flat head screw 16 PCS wings, M4x10 flat head screw. M6 x 20 socket head screw 12 PCS Attaches mount bars to rolling floor stand.
  • Page 6 FHDQ135 Floor Stand Parts List (4/4) Item Parts Name Image Quantity Note For disassembly & assembly of M6*12 • 5mm Allen wrench tools 1 PCS screws.
  • Page 7 Pre-work for Assembling Floor Stand...
  • Page 8 Pre-work for Assembling Floor Stand Preparation matters Number of engineering personnel:at least two. • Tools and equipment needed: • 6 mm & 5 mm Allen wrench tools. Phillips screwdriver. Platform with dimensions of at least 2300 * 1600 * 580 mm. ≧...
  • Page 9 Pre-work for Assembling Floor Stand Assembling the mount bar of FHDQ135 Assemble two pieces of FHDQ135 mount bar. • Fixed assembled mount bar using M5 x 10 PHMS. • M5 x 10 PHMS * 2 Phillips screwdriver Step. 1 Step. 2 •...
  • Page 10 Floor Stand Assembly Instructions...
  • Page 11 Floor Stand Assembly Instructions 1. Take the vertical column module out of the shipping box • Take out the “Vertical column module" from the transport box and let its two casters support its weight on the ground. • Please avoid allowing the single caster of the "Vertical column module" to bear the impact of its own weight, as this may cause damage to the caster.
  • Page 12: Locking Casters

    Floor Stand Assembly Instructions 2. Locking casters Step. 2 Step. 1 • Rotate the four casters of the two Vertical column modules to the direction shown in the picture. Step. 2 • Lock the four casters of two vertical column modules so they are oriented and will not slide.
  • Page 13 Floor Stand Assembly Instructions 3. Set assembly plane FHDQ135 floor stand is stably laid flat on an elevated platform to start assembly. • As shown in the picture, carefully place the two Vertical column modules smoothly on the elevated assembly plane.
  • Page 14 Floor Stand Assembly Instructions Select the hole position of the required height to start assembly The FHDQ135 floor stand can hold the display at two heights, 2429mm 2529mm from the ground. The following • procedures show the lower rolling floor stand assembly. If mounting the desired height of...
  • Page 15 Floor Stand Assembly Instructions Assemble the upper Main support beam parts Step 1: make sure the arrow symbol of the Main support beam part is pointing up. • Step 2: Insert the positioning pin of Main support beam into the corresponding •...
  • Page 16 Main support beam & Vertical column modules on the upper & lower sides must be consistent to successfully mount the FHDQ135 display. Step 3: Tighten the four M4 x 10 screws as shown in the picture, the torque value is 40 kgf.cm.
  • Page 17 Floor Stand Assembly Instructions Assembling the Right wing beam parts Step 1: make sure the arrow symbol of the Right wing beam part is pointing up. • Step 2: As shown in the picture, insert the positioning pin of Right wing beam into the •...
  • Page 18 Floor Stand Assembly Instructions Assembling the Left wing beam parts Step 1: make sure the arrow symbol of the Left wing beam part is pointing up. • Step 2: As shown in the picture, insert the positioning pin of Left wing beam into the •...
  • Page 19 Floor Stand Assembly Instructions Improve the robustness of assembled stand In the 8 positions shown in the figure, use M8 x 12 SHCS w/ M8 flat washer to firmly • combine Vertical column module, Main support beam, and wing beam into one. M8 x 12 SHCS * 8 M8 flat washer * 8 Torque value of fastening screw: 195 kgf.cm...
  • Page 20 Floor Stand Assembly Instructions Installing Mount Bars to Floor Stand (1/3) As shown in the picture, pass the positioning holes of the mount bar through the positioning pins of the floor stand beam to place it in • the correct installation position.
  • Page 21 Floor Stand Assembly Instructions Installing Mount Bars to Floor Stand (2/3) Use the beam's positioning pin to correctly limit the position and • assemble the mount bars. As shown in the picture, slide the Mount bars that runs through • the stand positioning pin to the right to the end.
  • Page 22 Floor Stand Assembly Instructions Installing Mount Bars to Floor Stand (3/3) Installing M6 X 20 SHCS w/ lock and flat washer plus large M6 flat washer in locations • shown. M6 x 20 SHCS * 12 M6 flat washer * 12 Fastening M6 x 20 SHCS using 5 mm Allen wrench with target torque value of 118 kgf.cm.
  • Page 23 Floor Stand Assembly Completed...