Installation Guide 756
4/26/2013
Eclipse AutoTite Automatic Gas
Shut-Off Valves
2000AT Series
Version 2

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the AutoTite 2000AT Series and is the answer not in the manual?

Questions and answers

Summary of Contents for Eclipse AutoTite 2000AT Series

  • Page 1 Installation Guide 756 4/26/2013 Eclipse AutoTite Automatic Gas Shut-Off Valves 2000AT Series Version 2...
  • Page 2: Disclaimer Notice

    Please send your corrections and comments to our Technical Documentation Specialist. PRODUCT NAME - SIZE It must be understood that Eclipse’s liability for its product, whether due to breach of warranty, negligence, strict liability, or otherwise is limited to the furnishing of ECLIPSE COMBUSTION, INC replacement parts.
  • Page 3: Table Of Contents

    Actuator Installation......................7 Actuator Mounting ........................ 7 Actuator Wiring........................8 Operation Checkout ......................10 3 Maintenance & Troubleshooting..................11 Introduction........................... 11 Maintenance......................... 11 Replacement Parts....................... 11 Troubleshooting Procedures ....................11 Eclipse AutoTite Automatic Gas Shut-Off Valves, V2, Installation Guide 756, 4/26/2013...
  • Page 4: Introduction

    Proof-of-Closure switches and one Auxiliary Switch. The Proof-of-Closure Switches are factory set non-field adjustable SPDT switches. The Auxiliary Switch is not a safety switch and is also a factory set non-field adjustable SPDT switch. Eclipse AutoTite Automatic Gas Shut-Off Valves, V2, Installation Guide 756, 4/26/2013...
  • Page 5: Additional Features

    Purpose The purpose of this manual is to make sure that you carry out the installation of a safe, effective and trouble-free system. Eclipse AutoTite Automatic Gas Shut-Off Valves, V2, Instruction Manual 756, 4/26/2013...
  • Page 6: Installation

    • Do not remove the protective plastic cap from the top of the valve until just before installing the properly. actuator. Eclipse AutoTite Automatic Gas Shut-Off Valves, V2, Installation Guide 756, 4/26/2013...
  • Page 7: Actuator Installation

    5. Tack weld the flanges to the pipe using a suitable filler material which is compatible with the ASTM A105 forged steel flanges and the steel pipe being used (probably ASTM A53 or A106). Eclipse AutoTite Automatic Gas Shut-Off Valves, V2, Installation Guide 756, 4/26/2013...
  • Page 8: Actuator Wiring

    Catalog Number 370, when attaching rigid and times (with the main manual gas shut-off valve intermediate type conduit. closed) by energizing and de-energizing the actuator to open and close the valve. Eclipse AutoTite Automatic Gas Shut-Off Valves, V2, Installation Guide 756, 4/26/2013...
  • Page 9 Auxiliary switch open position, normally open (NO) terminal Green Ground terminal (earth connection) White-black stripe Proof-of-closure, switch 2, common (C) terminal Black Hot terminal (L1) Figure 2.6 External Wire Connections Eclipse AutoTite Automatic Gas Shut-Off Valves, V2, Installation Guide 756, 4/26/2013...
  • Page 10: Operation Checkout

    All tests to be performed by a trained technician. Close all manual shut-off valves as soon as trouble occurs. Failure to do so could result in explosion. Eclipse AutoTite Automatic Gas Shut-Off Valves, V2, Installation Guide 756, 4/26/2013...
  • Page 11: Maintenance & Troubleshooting

    Valve body not field serviceable; replace valve and actuator. Switch not made Mechanical/electrical failure Cycle valve (open/close) while checking valve with multi-meter. Contact Eclipse. Switch is incorrectly wired Check power to switch. Rewire switch. Eclipse AutoTite Automatic Gas Shut-Off Valves, V2, Installation Guide 756, 4/26/2013...
  • Page 12 Installation Guide 756, 4/26/2013...

Table of Contents