MODEL E8S/SP
All information included in this publication is based on the latest information available at the
time of printing. CodeLine reserves the right to make changes at any time without notice and
without incurring any obligation whatsoever. Photocopying of this publication by authorized
original equipment manufacturers who have purchased directly from CodeLine, or by persons
using the materials for legitimate educational purposes, is approved by CodeLine. Otherwise all
copyright protection afforded by the law applies.
Product Bulletin 519014
USER’S GUIDE
E8H/SP & E8S/SP
Side Ported Pressure Vessels
For Reverse Osmosis
1000
PSI
MODEL E8H/SP
Chardon, Ohio Phone: 440-286-4116 • Fax 440-286-7532
Goa, India Phone: 91-832-2883300 • Fax 91-832-2883312
Ontario, California • Shanghai, China • New Delhi, India • Dubai,
U.A.E.
Milan, Italy
Regent Hills, Australia
www.codeline.com
1200
PSI
Copyright© 1999

Advertisement

Table of Contents
loading

Summary of Contents for Pentair CodeLine E8H/SP

  • Page 1 USER’S GUIDE E8H/SP & E8S/SP Side Ported Pressure Vessels For Reverse Osmosis MODEL E8H/SP MODEL E8S/SP 1200 1000 All information included in this publication is based on the latest information available at the time of printing. CodeLine reserves the right to make changes at any time without notice and without incurring any obligation whatsoever.
  • Page 2 PREFACE E8 Series Sidewall Ported RO pressure vessels are designed for continuous long term use as housings for reverse osmosis membranes. Typically, the pressure rating, overall length and total number of vessels is determined by calculations used during membrane element section. Vessels are installed into a system frame that provides the recommended support points and then strapped snugly to the frame using provided mounting hardware.
  • Page 3: Table Of Contents

    CONTENTS SECTION 1 OPERATION / MAINTENANCE GUIDE OM-1 Safety Precautions………………………………………. OM-3 Installation Notes……………………………………….. OM-4 Pre-pressurization Checklist……………………………. OM-5 Opening Vessel…………………………………………. OM-6 Replacing Elements…………………………………….. OM-9 Closing Vessel…………………………………………...OM-13 Head Rebuilding………………………………………...OM-18 Preventive Maintenance…………………………………OM-25 Trouble Shooting………………………………………...OM-26 SECTION 2 INSTALLATION GUIDE Handling and Receiving……………………………………..I-2 Mounting Shell.…………………………………………….. I-3 Piping Connections………………………………………….I-5 SECTION 3 APPLICATION GUIDE Suitability for Intended Use………………………………A-2...
  • Page 4 We recommend that only qualified mechanic experienced in servicing high-pressure hydraulic systems, open, close and service this vessel. This section is a guide to proper operation and maintenance of Pentair Water E8S/SP, E8H/SP pressure vessels. Good industrial practice must be used in applying this information to assure safe vessel use.
  • Page 5 Read and follow all instructions carefully. Pay particular attention to the safety precautions given in this Operation and Maintenance section. Should any information in this guide not agree with the system supplier’s instructions, call Pentair Water for clarification.
  • Page 6: Safety Precautions

    SAFETY PRECAUTIONS Read understand and follow every part of this section. Failure to take every precaution may void warranty and could result in explosive head failure. Install in an area where water leakage resulting from a vessel or piping malfunction would not damage sensitive or expensive equipment, such as electronic components.
  • Page 7: Installation Notes

    INSTALLATION NOTES Even though your vessel may have been installed by others, there are a few installation checks that you should make before system start up. Vessels must be installed correctly to ensure safe use and long service life. Check that vessels mounted on horizontal support frame using compliant black urethane saddles;...
  • Page 8: Pre-Pressurization Checklist

    PRE-PRESSURIZATION CHECKLIST DANGER – HIGH PRESSURE DEVICE Operation of this vessel may cause loss of life, severe bodily harm, and /or property damage if not correctly installed operated and maintained. Read and understand all guidelines given before attempting to open, operate or service this vessel. Failure to follow these guidelines and observe every precaution may result in malfunction and could result in explosive head failure.
  • Page 9: Opening Vessel

    OPENING VESSEL Step-By-Step Guide NOTE Read all guidelines in this section before attempting to open the vessel. WARNING DO NOT ATTEMPT TO SERVICE ANY COMPONENT WITHOUT FIRST VERIFYING THAT VESSEL PRESSURE IS FULLY RELIEVED FROM THE VESSEL. WARNING ATTEMPTING TO REMOVE ANY COMPONENT BEFORE PRESSURE IS RELIEVED MAY RESULT IN EXPLOSIVE RELEASE OF HEAD.
  • Page 10 Do not strike or apply undue force on the Permeate port / plug. NOTE If vessel has been in service for some time, the head may be difficult to remove. For assistance in head removal, E8 Series head tool (p/n 107028-1) is available from Pentair Water. STEP 5 REMOVE HEAD STEP 5A REMOVAL BY HAND 1.
  • Page 11 STEP 5B REMOVAL USING E8 SERIES HEAD TOOL 1. Insert the tool into the shell with threaded rods in line with bearing plate holes. 2. Thread the rods into the bearing plate holes and turn until the knobs bottom out. 3.
  • Page 12: Replacing Elements

    REPLACING ELEMENTS NOTE Read all parts of this section before replacing elements. These procedures are provided for general information only. Elements should be installed in accordance with the element manufacturer’s recommendations. WARNING DO NOT ATTEMPT TO SERVICE ANY COMPONENT WITHOUT FIRST VERIFYING THAT VESSEL PRESSURE IS FULLY RELIEVED FROM THE VESSEL.
  • Page 13 CAUTION Do not scratch or damage vessel bore when removing or installing elements. WARNING DO NOT PRESSURIZE VESSEL WITH OUT ELEMENTS INSTALLED OR OTHERWISE OPERATE VESSEL WITH PERMEATE PORT PRESSURE IN EXCESS OF 125 PSI. OPERATION IN EXCESS OF THIS PRESSURE COULD RESULT IN CATASTROPHIC PORT FAILURE.
  • Page 14 CAUTION Maintain element alignment carefully during assembly process. Do not allow element weight to be supported by interconnector. Misalignment can result in damage to interconnectors or permeate tubes or to element outer surface. NOTE Take care to avoid pushing elements too far as it can be difficult to push the stack in a reverse direction.
  • Page 15 WARNING CONNECT THE CENTRAL (PERMEATE) TUBE OF THE MEMBRANE ELEMENT STACK, WITH AN ADAPTER ON EACH END, TO THE PERMEATE PORT IN THE HEAD AT BOTH ENDS OF VESSEL. PRESSURIZING VESSEL WITHOUT BOTH ADAPTERS INSTALLED COULD RESULT IN EXPLOSIVE HEAD FAILURE. STEP 4 INSTALL ELEMENT INTERFACE HARDWARE Assemble adapter to element permeate tube at each end of vessel.
  • Page 16: Closing Vessel

    CLOSING VESSEL Step- By- Step guide NOTE Read all guidelines in this section before attempting to close the vessel. WARNING CHECK THE HEAD ASSEMBLY FOR CORROSION AS DESCRIBED IN THE HEAD REBUILDING SECTION. CORRODED PARTS CAN RESULT IN CATASTROPHIC FAILURE. DO NOT PRESSURIZE THE VESSEL UNTIL AFTER VISUALLY INSPECTING TO ENSURE THAT ALL THREE SEGMENTS OF THE LOCKING RING SET ARE FULLY SEATED AND HELD IN PLACE BY SECURING RING AND SCREWS.
  • Page 17 NOTE Contact Pentair Water for guidance, if damage to the vessel’s internal surface or Feed/ Concentrate port, seals or attachments are discovered during inspection. NOTE Never attempt to repair a fiberglass shell STEP 2 SHELL AND HEAD SEAL LUBRICATION Work O-ring lubrication into the shell from half way up the bevel to approximately ½” in from the bevel.
  • Page 18 NOTE If an E8 series head tool (p/n 107028-1) is available, it can be used to ease head installation. (The tool can be obtained from Pentair Water). If a tool is not available, proceed as follows. WARNING INTERLOCKING COMPONENT MUST BE CORRECTLY INSTALLED. INCORECT ASSEMBLY OR INSTALLATION CAN RESULT IN EXPLOSIVE HEAD FAILURE.
  • Page 19 NOTE CAUTION Before inserting securing screws, it is advisable to lightly coat the screw threads with Locking ring segments must be installed with stepped edge facing outwards. anti-seize compound, to ease later disassembly. NOTE If holes in securing ring and bearing plate do not align precisely, reversing the securing ring should improve alignment.
  • Page 20 STEP 5 RECONNECT PERMEATE PIPING Reconnect manifold piping to the vessel Permeate port. STEP 6 PRE-PRESSURIZATION CHECKS It is vitally important that the following checks be carried out before any attempt is made to pressurize the vessel. It is recommended that the Pre-Pressurization Checklist be used to systematically verify that all steps have been performed.
  • Page 21 HEAD REBUILDING – E8S/SP AND E8H/SP Step- By- Step guide NOTE Read all guidelines in this section before attempting to rebuild the head. Head rebuilding should be performed in a clean work area. Dust or dirt on O- rings or other part can scratch inner surface and cause subsequent leakage. WARNING DO NOT SERVICE ANY COMPONENT UNTIL YOU VERIFY THAT VESSEL PRESSURE IS FULLY RELIEVED FROM THE VESSEL.
  • Page 22 STEP 2 REMOVE PERMEATE PORT RETAINING RING Remove the Permeate port retaining ring located on the external side of the bearing plate. a. A retaining ring removal tool is available from Pentair Water part number 6MM001-2. STEP 3 REMOVE THE PERMEATE PORT Remove the Permeate port by pressing it out from the external side of the bearing plate.
  • Page 23 In combination with good industrial practice, these guidelines provide a basis for safe system operation. Any condition not covered in this section should be referred to Pentair Water. Corrosion in this context includes metal oxidation products and mineral deposits.
  • Page 24 SECURING SCREWS with stripped head or thread. LOCKING RING SEGMENTS bent or damaged. Any other detail considered to be a potential problem should be referred to Pentair Water. CAUTION This procedure for evaluating corroded components is to be used on any corroded metal parts.
  • Page 25 1. Examine all components for corrosion. For any components not in “as-new” condition, proceed as follows: Loosen any large deposits with small wire brush. Place components in shallow container of soapy water and scrub entire surface with ® medium grade Scotchbrite until all corrosion is removed.
  • Page 26 Excessive lubricant may foul the membrane. Do not use petroleum-based lubricant. NOTE It is recommended that all seals must be replaced each time the head is assembled. A seal replacement kit is available from Pentair Water. NOTE Lubricate seals using non-petroleum based lubricants, i.e Parker Super O-Lube ®...
  • Page 27 STEP 3 ASSEMBLE THE BEARING PLATE AND SEALING PLATE. Fit the Bearing Plate over the smaller diameter end of the Permeate port and press to fully seat against the sealing plate. The Bearing Plate side with slightly smaller diameter should face the Sealing Plate. When installed correctly, the smallest outside diameter and the danger label should face outward.
  • Page 28: Preventive Maintenance

    PREVENTIVE MAINTENANCE Corrosion prevention is essential for the maintenance of safe operating conditions and to ease membrane element servicing. Attention to the points listed below will enhance long-term safe operation and will ease servicing. For suggestions on cleaning corrosion deposits from the vessel inside surface, refer to Closing Vessel.
  • Page 29: Trouble Shooting

    Do not use a wire brush on components made from plastic, fiber glass or PVC materials NOTE Recommendations listed below are intended only as a guide. If the head assembly is still difficult to remove after all recommendations have been followed call Pentair water for technical assistance CAUTION When applying penetrating fluid, be careful to avoid element contamination.
  • Page 30 2. Jacking screws cannot be threaded through the securing ring due to excessive corrosion or damage. A. Clean any corrosion from the Jacking screw holes and thread a 5/16-18 bottoming tap into the hole. B. If the securing ring still does not break lose repeat step 1. CAUTION When applying penetrating fluid, be careful to avoid element contamination.
  • Page 31 NOTE If the head assembly will not release from the shell after all recommendations have been followed, call Pentair Water for technical assistance. HEAD ASSEMBLY 1. Will not release from shell even with use of head puller tool (p/n 107028-1): A.
  • Page 32 SUDDEN DROP IN PERMEATE QUALITY If a system is started and stopped frequently and no provision is made to raise the pressure slowly, movement of the membrane column may damage O-ring seals and reduce permeate quality. If the quality of the permeate suddenly drops off, and poor membrane performance is not suspected, remove the head as per instructions in the User’s Guide (See OPENING VESSEL section).
  • Page 33: Section 2 Installation Guide

    Read and follow all instructions carefully. Pay particular attention to the safety precautions given in this Operation and Maintenance section. Should any information in this guide not agree with the system supplier’s instruction, call Pentair Water. TABLE OF CONTENTS...
  • Page 34: Handling And Receiving

    Exterior vessel damage can lead to early vessel failure. Damage received in shipment should be reported to the shipping company immediately upon receipt. Minor damage such as scratches that go no deeper than the paint may be acceptable. Call Pentair Water for advice if in doubt.
  • Page 35 MOUTING SHELL NOTE If mounting vessel for the first time, see “Piping Recommendations for CodeLine E8 Series Sideport Vessels”. . This section is concerned with the mounting of E8S/SP and E8H/SP Series pressure vessels only. These guidelines must be integrated with any additional procedures required for specific installation.
  • Page 36 Place mounting straps over vessel with cork strip against vessel. Provide adequate room for servicing at both ends of vessel. Elements are installed and removed in the direction of feed flow. Position screw through the frame mounting holes into strap nuts and run up to the frame finger tight.
  • Page 37: Piping Connections

    PIPING CONNECTIONS The following are suggested guidelines to ensure that the vessel is allowed to expand and is easily serviced. Support the header and interconnecting piping in a manner that they are self-supporting. Connecting piping alignment to feed, Concentrate and Permeate ports should not exceed 0.030-in.
  • Page 38: Section 3 Application Guide

    E8S/SP & E8H/SP series vessel selected is appropriate to that application. Pentair Water will assist the purchaser in determining the suitability of the standard vessel for their specific operating conditions. For non-standard applications, alternate materials are available on special order.
  • Page 39 Requirement for increased fire resistance in some circumstances (e.g may preclude use of PVC for permeate ports) Use of a Pentair Water pressure vessel other than its intended application will void the warranty. Pentair Water will assist the purchaser in determining the suitability of the standard vessel for their specific operating conditions.
  • Page 40: Elasticity And Mounting Requirements

    ELASTICITY AND MOUNTING REQUIREMENTS Mounting design must allow for vessel expansion both axially and radially. Although the expansion under pressure is slight, undue restriction can result in damage to the vessel and to other system components. Expansion is typically up to .020 inch in diameter and up to 0.007 inch per foot in length.
  • Page 41: Corrosion

    Leaks from vessel or nearby components, which allow head parts to be routinely wetted, should not be tolerated. The following typical list of Pentair pressure vessel components shows the standard material of construction of each part. An evaluation of the possibility of corrosion damage to metal head interlock components is of critical importance.
  • Page 42: Safety

    SAFETY CAUTION Pressure vessels may cause loss of life, severe bodily harm or property damage if not correctly installed, operated and maintained. Safety in service of fiberglass pressure vessels depends on proper application, installation, operation and maintenance. This section is intended to provide guidance towards safe system design.
  • Page 43 APPENDIX TABLE OF CONTENTS Pre-Pressurization Checklist Piping Recommendations Limited Warranty Registration Card APX-1...
  • Page 44: Pre-Pressurization Checklist

    PRE-PRESSURIZATION CHECKLIST Danger – High Pressure Device Operation of this vessel may cause loss of life, severe bodily harm, and /or property damage if not correctly installed or maintained. Read and understand all guidelines given before attempting to open, operate or service this vessel. Failure to follow these guidelines and observe every precaution may result in malfunction and could result in explosive head failure.
  • Page 45: Piping Recommendations

    Piping Recommendations for CodeLine E8 Series Side ported Vessels Various methods of connecting sideport vessels to manifolds are possible. The recommended method is to connect each vessel side port to the manifold using two flexible Victaulic® joints and an intermediate piping section. A 90 o -elbow would be ideal, however, a straight piping connection would also be acceptable.
  • Page 46 Piping Recommendations continued An alternate method using a single Victaulic® is acceptable but requires more thoughtful execution. The manifold must be fabricated using close tolerances to help ensure correct alignment. Installation must follow a sequence of assembly steps to initially ensure correct shell to manifold alignment.
  • Page 47 Piping Recommendations continued Even though a single Victaulic® coupling arrangement may be the choice for low cost and compactness, it brings with it the necessity to provide the required amount of flexibility in some other way. A Victaulic® coupling allows angular but not lateral misalignment. Two rigidly restrained pipes not lying on a common axis can be forced to align if the fit is close enough to allow the two halves of the coupling to be pulled together by the bolts.
  • Page 48: Warranty

    WARRANTY The seller warrants that the goods supplied shall conform to CodeLine specifications and shall be free from defect in material or workmanship. The warranty expires one (1) year from the date of invoice. If the buyer discovers within this period a failure of the product to conform to specifications, or a defect in material or workmanship, the buyer must promptly notify the seller in writing.
  • Page 49 REGISTRATION CARD Vessel Model: Serial Numbers Numbers are located at one end of vessel. Date of Purchase: (If more than 30 numbers, please attach.) OEM Purchased From: Type of System: Membrane Softening Ultrafiltration Brackish RO Seawater RO Other: Size of System: GPD/No.