Start-Up Checklist - Bryant 559K 08 Series Service And Maintenance Instructions

Single package rooftop electric cooling unit with puron (r-410a) refrigerant 7.5 to 15 nominal tons
Table of Contents

Advertisement

NOTE: To avoid injury to personnel and damage to equipment or
property when completing the procedures listed in this start-up
checklist, use good judgment, follow safe practices, and adhere to
the safety considerations/information as outlined in preceding sec-
tions of this Installation Instruction document.
I. PRELIMINARY INFORMATION
MODEL NO. ___________________________________________
JOB NAME _____________________________________________
SERIAL NO. ____________________________________________
ADDRESS _____________________________________________
START-UP DATE________________________________________
TECHNICIAN NAME _____________________________________
ADDITIONAL ACCESSORIES_________________________________________________________________________________
_________________________________________________________________________________________________________
II. PRE-START-UP
Verify that all packaging materials have been removed from unit
Verify installation of outdoor air hood
Verify that condensate connection is installed per instructions
Verify that all electrical connections and terminals are tight
Check that indoor-air filters are clean and in place
Check that outdoor air inlet screens are in place
Verify that unit is level
Verify that fan assembly is free of obstructions and rotor spins freely
Verify that scroll compressors are rotating in the correct direction
Verify installation of thermostat
III. START-UP
ELECTRICAL
Supply Voltage
Supply Voltage to Ground
Compressor Amps 1
Compressor Amps 2
Supply Fan Amps
TEMPERATURES
Outdoor-air Temperature
Return-air Temperature
Cooling Supply Air Temperature
Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Catalog No. 04-53559012-01

START-UP CHECKLIST

559K*08-16 Single Package Rooftop
Electric Cooling Units
(Remove and use for job file)
L1-L2_____________
L1 to Ground _______
L1 ______________
L1 ______________
L1 ______________
_____________ °F DB
_____________ °F
Printed in U.S.A.
Form No. SM559K-8-16-01
L2-L3_____________
L2 to Ground _______
L2 ______________
L2 ______________
L2 ______________
_____________ °F DB (Dry Bulb)
_____________ °F WB (Wet Bulb)
Pg CL-1
11-23
(Y/N) _____
(Y/N) _____
(Y/N) _____
(Y/N) _____
(Y/N) _____
(Y/N) _____
(Y/N) _____
(Y/N) _____
(Y/N) _____
(Y/N) _____
L3-L1_____________
L3 to Ground _______
L3 ______________
L3 ______________
L3 ______________
Replaces: New

Advertisement

Table of Contents
loading

This manual is also suitable for:

559k 16 series

Table of Contents