Earthquake anchoring kit only for MEGR-MC

Where seismic installations are planned, the machines must be installed in a suitable manner:
o
Avoid installations with vertical air flow.
o
Pay particular attention to the anchoring to the support structure (refer to the technical manual).
The anti-seismic version of the machine is equipped with a reinforced structure already assembled at the factory and must be selected
at the time of order.
4.6.5

Cooling/electrical connections in seismic areas

Avoid rigid connections between the machine and the system; it is necessary to isolate the machine with a flexible system that allows
free movement in the event of an earthquake.
The cooling / electrical connection is the responsibility of the installer; the choice of flexible components and installation must follow
the instructions of the designer responsible for the system.

5 PRE-COMMISSIONING

5.1 Before starting the unit

Before contacting the Specialist Engineer, who will execute the first commissioning running test, the Installer must carefully check
that the installation complies with the requirements and specifications set-out during the design stage, making sure that:
the electrical connection is correct, and that it guarantees compliance with the current Electromagnetic Compatibility
Directive;
the cooling connection is correctly terminated;
there are no leaks in the cooling circuit;
all shut-off valves are open.