1 Safety
1.2

Recommendations

6
200 Combi 2
Caution
Only qualified professionals are authorised to work on the boiler
and the installation.
The appliance has an integral frost protection mode as long as
there is power to the boiler.
Important
Regularly check the water pressure in the system
(recommended pressure is 1.5 bar).
Keep the appliance accessible at all times.
Do not remove or cover the user information and serial number
labels affixed to the boiler control flap. They must remain legible
throughout the lifetime of the boiler.
1.2.1

The Benchmark Scheme

Baxi Heating UK Ltd is a licensed member of the Benchmark Scheme
which aims to improve the standards of installation and commissioning of
domestic heating and hot water systems in the UK and to encourage
regular servicing to optimise safety, efficiency and performance.
Benchmark is managed and promoted by Heating and Hotwater Industry
Council. For more information visit www.centralheating.co.uk
1.2.2

Benchmark Commissioning Checklist

Please ensure that the installer has fully completed the Benchmark
Checklist on the inside back pages of the installation instructions supplied
with the product and that you have signed it to say that you have received
a full and clear explanation of its operation. The installer is legally required
to complete a commissioning checklist as a means of complying with the
appropriate Building Regulations (England and Wales).
All installations must be notified, by the installer, to Local Area Building
Control either directly or through a Competent Persons Scheme. A
Building Regulations Compliance Certificate will then be issued to the
customer who should, on receipt, write the Notification Number on the
Benchmark Checklist.
This product should be serviced annually to optimise its safety, efficiency
and performance. The service engineer should complete the relevant
section of the Benchmark Service Record in the Installation & Service
manual after each service.
The completed Benchmark Checklist & proof of annual servicing (where
applicable) will be required in the event of any warranty work.