Installation Sequence - A.O. Smith BTH 120-250(A) Installation & Operating Instructions Manual

Series 970 and 973 commercial gas water heater gas-fired power burner for domestic hot water
Table of Contents

Advertisement

IMPORTANT
WHEN LOCATING THE TERMINALS ON A SIDEWALL, THE FOLLOWING
SPECIFICATIONS PERTAINING TO TERMINAL LOCATION MUST BE
FOLLOWED.
1. The intake vent terminal and the exhaust vent terminal must terminate on
the same exterior wall and must be located at a minimum of 24" (61cm)
from the vertical centerline of the exhaust vent terminal (see Figure 9).
In colder climates increasing the 24" (61cm) minimum will reduce
possibility of frost over from side winds blowing exhaust vapors to the
air intake of the direct the vent.
2. The horizontal centerline of the intake vent terminal may not be located
lower than the horizontal centerline of the exhaust vent terminal
(see Figure 9).

INSTALLATION SEQUENCE

For installations in the City of Los Angeles, California Category IV PVC Pipe
such as that manufactured by Brownline Pipe Company, must be used as
vent pipe material
Vent terminals supplied with the heater must be used.
NOTE: BEFORE BEGINNING INSTALLATION OF ANY VENT PIPE READ THE
VENT PIPE MANUFACTURER'S INSTALLATION INSTRUCTIONS.
1. After the points of termination have been determined, use the cover
plates as templates to mark the holes for the vent pipes to be inserted
through the wall. BEWARE OF CONCEALED WIRING AND PIPING INSIDE
OF WALL.
2. If the vent terminals are being installed on the outside of a finished wall,
it may be easier to mark both the inside and outside wall. Align the holes
by drilling a hole through the center of the template from the inside
through to the outside. The template can now be positioned on the
outside wall using the drilled holes as a centering point for the template.
3. A) MASONRY SIDE WALLS
Chisel an opening approximately 1/2" (1.3 cm) larger than the marked
circle.
B) WOODEN SIDE WALLS
Drill a pilot hole approximately one quarter inch outside of the marked
circle. This pilot hole is used as a starting point for a saws-all or sabre
saw blade. Cut around the marked circle staying approximately one
quarter inch outside of the line. (This will allow the vent pipe to easily
slide through the opening. The resulting gap will be covered by the vent
terminal cover plates.) Repeat this step on the inside wall if necessary.
4. Cut a length of 3" PVC pipe about 3.5" (8.9 cm) longer than the wall
thickness at the opening.
5. Glue the intake vent terminal to the section of the pipe.
6. Slide the wall plate over the pipe to stop against intake vent terminal.
7. Place a bead of caulking (not supplied) around the gap between the
pipe and the wall. Place some of the caulking on the back of the plate to
hold it against the wall after installation.
8. If the vent pipe is installed up to the wall, with a coupling on the end
against the wall opening, the pipe with the vent terminal can be
prepared for gluing before inserting through the wall. Slide the pipe
through the wall and insert into coupling on the other side of the wall,
making sure that the vent terminal ends up pointed in the correct position
(Figure 10).
FIGURE 9
CAUTION
9
FIGURE 10

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents