Circuit Breaker Operator Tasks; Checks Of The Primary Power Path; Cleanliness Check; Primary Disconnects - Siemens DPU Series Instructions, Installation, Operation, Maintenance

Vacuum circuit breakers (vehicle)
Table of Contents

Advertisement

Maintenance
2. The second step in the removal procedure is to de-en-
ergize control power to the circuit breaker. Open the
control power disconnect device.
3. Rack the circuit breaker to the "DISCONNECT" position.
4. Perform the spring discharge check. This is done by
first pressing the red Trip pushbutton. Second, press
the black Close pushbutton. Third, press the red Trip
pushbutton again, and observe the spring condition in-
dicator. It should read Discharged (Refer to Circuit
Breaker Operator / Manual E50001-F710-A251-V3-4A00).
5. Remove the circuit breaker from the switchgear.

Circuit Breaker Operator Tasks

Perform tests as described in manual E50001-F710-A251-
V3-4A00.

Checks of the Primary Power Path

Refer to Circuit Breaker Operator Manual E50001-F710-
A251-V3-4A00.

Cleanliness Check

Refer to Circuit Breaker Operator Manual E50001-F710-
A251-V3-4A00.
In addition to the circuit breaker operator, Figure 5 shows
a side view of the circuit breaker with the insulating barri-
ers removed in order to show the upper and lower pri-
mary disconnects.
These components must be clean and free of dirt and any
foreign objects. Use a dry lint free cloth. For stubborn dirt,
use a clean cloth saturated with denatured alcohol (except
for the vacuum interrupters). For stubborn dirt on a
vacuum interrupter use a damp cloth and then thoroughly
dry using a dry lint free cloth.
The phase barriers are plates of glass polyester insulating
material which are attached to the circuit breaker to pro-
vide suitable electrical insulation between the vacuum in-
terrupter primary circuits and the switchgear.
Always re-install the phase barriers carefully to their origi-
nal location prior to inserting the circuit breaker into the
switchgear.

Primary Disconnects

Figure 5 is a side view of the circuit breaker showing the
upper and lower primary disconnects.
Inspect the primary disconnect arms for physical integrity
and absence of mechanical damage. Any evidence of burn-
ing or pitting would indicate weakness of the contact fin-
ger springs.
Using a clean cloth saturated with denatured alcohol, clean
old lubricant from primary disconnects, and apply contact
lubricant (part #15-172-791-233) in a thin layer.

Fastener Check

Inspect all fasteners for tightness. Replace any fasteners
that appear to have been frequently removed, show dam-
age or are missing.
Figure 5. Primary Power Path

Electrical Control Checks:

Wiring and Terminals Check
Refer to Circuit Breaker Operator Manual E50001-F710-
A251-V3-4A00.
Secondary Disconnect Check
In addition to checking the terminals of the secondary dis-
connect, ensure that secondary disconnect assembly
moves freely and is aligned for proper engagement.
Automatic Spring Charging Check
Refer to Circuit Breaker Operator Manual E50001-F710-
A251-V3-4A00.
Electrical Close and Trip Check
Refer to Circuit Breaker Operator Manual E50001-F710-
A251-V3-4A00.
Vacuum Integrity Check
Refer to Circuit Breaker Operator Manual E50001-F710-
A251-V3-4A00.
High Potential Test
Refer to Circuit Breaker Operator Manual
E50001-F710-A251-V3-4A00.
8

Advertisement

Table of Contents
loading

This manual is also suitable for:

Dpr series

Table of Contents