Inspection; General Directions; Preparing The Boiler For Inspection - Boulter Buderus benchmark 500-24/S Installation And Maintenance Instructions Manual

Wall-mounted condensing gas system boiler
Table of Contents

Advertisement

3

Inspection

3
Inspection
3.1

General directions

Do a visual and functional test of the installation.
3.2

Preparing the boiler for inspection

Disconnect the boiler from the mains power supply.
DANGER OF FATAL INJURY
due to electric shock when system is opened.
Before opening the system:
disconnect the heating unit at the emer-
gency OFF switch or the corresponding
circuit breaker of the house power supply.
Ensure that the heating system cannot be
reconnected by accident.
Remove the burner housing or cover from the heating
boiler.
NOTE
If the gas supply pipes are to be disconnected
from the burner, the housing MUST ONLY be
removed by a qualified service technician and
checked for tightness on reassembly.
3.2.1
Internal leak test
Disconnect the boiler from the mains power supply.
Do not allow the product to come into contact with the electrical
wiring.
3.2.2
Check the combustion chamber and heat
exchanger for pollution
3.2.3
Check the burner
3.2.4
Check the functioning and safety of the flue gas
exhaust
3.2.5
Check the pre-pressure of the expansion vessel
3.2.6
Check the hot water cylinder for leakage
3.2.7
Check the programming of the room thermostat
Subject to modifications resulting from technical improvements!
40
Boulter Buderus Ltd. • http://www.boulter-buderus.co.uk
Installation and maintenance instructions for Buderus 500 - 24/S • 03/2005

Advertisement

Table of Contents
loading

Table of Contents