Piping maintenance
During installation, provide maintenance as specified in the table in order to prevent water, foreign matter and dust
from entering the pipes.
Location
Work period
More than 1 month
Outdoors
Less than 1 month
Indoors
——
Note
Particularly when a pipe is to penetrate through a wall or extend to outdoors, make sure foreign matter and dust
etc cannot enter the pipe.
Attention item for piping connection
• To connect a pipe to or remove it from the connection kit, do use pliers for screws and torque spanner;
• When installing the connection kit, please fix the box and connecting pipes in an efficient way to avoid shaking
when changing connection kit.
• For the sizes of the flares, please refer to <Table-1>.
<Note>
• For connection at a flare, apply ester or ether oil to the flare (both inner surface and outer surface). Apply such oil
for 3 to 4 times and insert the screw in the first use
• The tightening torque for the flare is given in <Table-1>.
If no torque wrench is available, act as the follows.
Use a spanner to tighten the nut of the flare to a position where the tightening torque sharply increases.
The tightening angle for the position where the tightening torque sharply increases <Table -2>.
After the work, make sure there is no air leakage.
<Table-1>
Tube size
Tightening torque (N.m) Machined flare size A (mm)
Ø6.35
14.2~17.2
Ø9.52
32.7~39.9
Ø12.7
49.5~60.3
Ø15.88
61.8~75.4
Ø19.05
97.2~118.8
Maintenance method
Screw
Screw or strap
8.7~9.1
12.8~13.2
16.2~16.6
19.3~19.7
23.7—23.9
20
Flare shape