6.3.5 CONTROL
The controller is operated exclusively via the touch control. Service settings are performed by the appropriate service program, which is only
available to trained and certified companies.
Touch control CP for Digireg
7. COMMISSIONING
The device may only be put into operation for the first time by a suitably qualified specialist.
7.1 INSTALLATION AND CONNECTION CHECK
Before the first commissioning, it is necessary to check:
–
Equipment cleanness, installation completeness/quality
–
Fan free rotation
–
Operating voltage of installed control system
–
Operating voltage of electric motor acc. to type plate
–
Actuator control and operating voltage
–
Function of condensate drain and trap water flooding
–
Cleanness of filter cartridges
–
Flap movability
–
Tight connection to distribution lines
–
Closing of all doors and service holes
Any faults must be rectified before starting the unit for the first time.
7.2 TRIAL OPERATION
The material content of the comprehensive testing includes the commissioning of the device for a pre-agreed time and its continuous
inspection. In order to comply with the required air parameters depending on the operation of the building and the technology, it is necessary to
fine-tune the device during the test operation, or during the warranty tests.
For the first start of the air handling unit, the company S&P UK Ventilation Systems, offers the STARTPACK assistance service package.
Find out about the conditions and scope of the STARTPACK package at
The company putting the unit into operation is obliged to demonstrably train the user's staff. Without proof of operator training, the warranty will not
take effect and the device must not be operated.
®