Installation
Fig. 31
[1]
Flue clamp
[2a & 2b] Flue section
▶ Push the air inlet section through the side panel opening into the air
box until it meets the stops [4] on the clamp assembly
▶ Centralise the inner elbow pipe within the elbow.
▶ Fit the elbow [3] onto the flue cowl.
▶ Tighten the clamp [1] onto the flue elbow.
1
3
Fig. 32
[3]
Elbow
[4]
Clamp stops
[5]
Clamp
▶ Drill through the tab [6] on the mounting bracket, with the 3.3mm
drill bit into the air inlet outer section and secure with a self-tapping
screw.
24
1
2a
2b
&
6720807912-11.1Wo
4
5
6720807912-12.1Wo
Fig. 33 Tab detail
5.4.4

All flue options, final assembly

▶ Lightly grease the flue pipe seal with the solvent free grease supplied.
▶ Remove the screw from the clamp bracket [1] and open the clamp.
▶ Insert the terminal [3] fully into the 80mmØ flue pipe.
▶ Pass the flue pipe [2] through the clamp bracket [1] and push into
the flue cowl or elbow.
Fig. 34 Final assembly
[1]
Clamp bracket
[2]
Flue pipe
[3]
Terminal
▶ Drill two holes into the terminal [3] through the tabs [5], with the
3.3mm drill bit, one either side, and secure the terminal [3] to the
tabs [5] using the two self tapping screws.
▶ Fit the air box cover [4] over the lip on the top of the air box and
secure the bottom two screws removed earlier.
Greenstar Heatslave II External
3.3mmØ
6
6720807912-13.1Wo
1
2
3
6720807912-17.1Wo
2022+
6 721 843 980 (2022/01)