Taylex ABS Installation Manual

Concrete advanced blower system
Hide thumbs Also See for ABS:

Advertisement

Quick Links

INSTALLATION MANUAL
CONCRETE ADVANCED BLOWER SYSTEM (ABS/ABSNR)

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the ABS and is the answer not in the manual?

Questions and answers

Summary of Contents for Taylex ABS

  • Page 1 INSTALLATION MANUAL CONCRETE ADVANCED BLOWER SYSTEM (ABS/ABSNR)
  • Page 2: Table Of Contents

    10. EXCAVATION & LIFTING INSTRUCTIONS .................8 a. ABS Standard Excavation Instructions .................8 b. ABS Standard Lifting Instructions ................9 c. ABS Tall 400 Excavation Instructions… ..............10 d. ABS Tall 400 Lifting Instructions… ................11 e. ABS Tall 600 Excavation Instructions… ..............12 ABS Tall 600 Lifting Instructions…...
  • Page 3: Introduction

    This manual has been put together to explain the installation process of the ABS system as a guide only. Some sites may differ in access and slope which need to be taken into account when delivering and installing the system.
  • Page 4: Standards & Licencing

    To ensure the ABS is installed in the position nominated by the Home Owner/ Builder, the location of the ABS should be marked out prior to excavation. The installer at this stage should have a copy of the approved site plans showing the location of the ABS as well as the required local authority approval.
  • Page 5: Delivery And Placement

    ABS will vary depending on the size of the crane. To enable the ABS to be unloaded, a minimum width of 7m (may vary depending on crane truck) will be required at the hole. This distance allows for the width of the crane truck, the width of the tank itself, and clearance for safe and free manoeuvring of the ABS into the excavated hole.
  • Page 6 Page 5 of 15...
  • Page 7: Installation

    Always ensure the installation location include the future landscaping provision allow for the diversion of stormwater and surface waters away from the system. The ABS comes with 3 different heights to accommodate invert levels as deep as 1270mm below ground level.
  • Page 8: Electrical Connection

    Ensure that sand or excavated material does not fall on the lid of the ABS as this will fall into the system through the manholes and clog the system and irrigation pump. Ensure that the backfill material is kept at least 100mm below the surface of the systems lid.
  • Page 9: Excavation & Lifting Instructions

    Inlet Outlet Lifting TRUCK ACCESS Hole Unloading of ABS via the back of the truck NOT SIDE. Ensure BACK of truck has clear level 6m wide access to the edge of the hole. 100mm Inlet REACH OF CRANE/ CRANE TRUCK To be determined by your crane/ crane truck operator.
  • Page 10: Abs Standard Lifting Instructions

    2. Lower chains through TOP lifting holes provided in the lid of the ABS. 3. Loop chains through the lifting holes directly below on the inside wall of the ABS. 4. Steel reinforcing bars have been installed inside the concrete for lifting purposes. Only lift this tank from these holes.
  • Page 11: Abs Tall 400 Excavation Instructions

    1. Dig hole 3000mm square & (refer to value of A* in the table) mm deep. 2. Ensure inlet drainage has a 1/60 fall to the inlet of ABS. Risers are available if the tank needs to be installed deeper in the ground to maintain fall.
  • Page 12: Abs Tall 400 Lifting Instructions

    Electrical Connection Diagram Taylex IMPORTANT INSTRUCTIONS • Dedicated 10amp Circuit Breaker in power board (Taylex Best Practise) ® • Hardwired with 2.5mm wire (ANE) Active, Neutral, Earth to Weatherproof GPO located in blower box • Connect the 12V to 240V power supply plug to the single GPO •...

This manual is also suitable for:

Absnr

Table of Contents