Download Print this page

Advertisement

Quick Links

Battery System Quick Start Guide
Battery System: SolarEdge Energy Bank and SolarEdge Energy
Note: Installation of the PV system is not within the scope of this document.
Disclaimer of Liability and Warranty: This pictorial guide does not replace installation manuals supplied
with the components. Solahart assumes no responsibility for loss, damage or expense resulting from
improper installation, handling or misuse of components. Refer to the warranty statement in the Solahart
Owner's guide for full warranty terms and conditions.
Installer Responsibilities
The installer is solely responsible for:
Observing and conforming to all relevant Australian Standards, all relevant Clean Energy Council
Accreditation guidelines and all applicable laws, ordinances, regulations, codes of practice and local
or national building codes, including any that may have superseded this guide.
Ensuring that the installation complies with AS/NZS 3000, AS/NZS 5139, AS/NZS 5033, AS 4777.1,
AS/NZS 1768, and any relevant electrical service and installation rules for the state or territory where
the system is installed.
Ensuring that the Battery system and associated components are appropriate for the particular
installation and the installation environment.
Hub Series Inverter
System Overview Diagram
Warnings

Advertisement

loading
Need help?

Need help?

Do you have a question about the SE3000H and is the answer not in the manual?

Questions and answers

Summary of Contents for Solahart SE3000H

  • Page 1 Disclaimer of Liability and Warranty: This pictorial guide does not replace installation manuals supplied with the components. Solahart assumes no responsibility for loss, damage or expense resulting from improper installation, handling or misuse of components. Refer to the warranty statement in the Solahart Owner’s guide for full warranty terms and conditions.
  • Page 2: Tools Required

    • Ensuring only parts supplied by Solahart Industries and installer supplied parts as specified by Solahart Industries are utilised (substitution of parts may void the warranty and invalidate certification). • Ensuring that mounting fasteners have adequate pull-out strength and shear capacities to suit the installation.
  • Page 3 Note: The Installation location of the Battery must also comply with the requirements of AS/NZS 5139. Cabling and Conduits Any earthing cable, AC cable and conduits are not supplied by Solahart and should be selected based on the following criteria.
  • Page 4: Communication Cabling

    Note: Rated current in backup operation are valid for installations with multiple inverters. For a single backup inverter operation, rated current in backup is 90% of the stated value COMMUNICATION CABLING Cable Description Cable Type Cable between Inverter and Meter CAT6 Cable between Meter and CT CAT6...
  • Page 5 Unpacking and Mounting Battery Refer to SolarEdge Home Battery User Manual for further mounting instructions. Unpack contents from the SolarEdge battery packaging as per instruction Warning: Battery modules are heavy (approximately 121 kg each). It is recommended that the installation is done by two people. Floor mounting: Parts for the Floor Stand Base Mount and Back Holder are supplied as part of the SolarEdge Home Battery Floor Mount kit...
  • Page 6 11. (Optional) Insert a floor connector bracket between the bracket securing nut and the foot of each leg. Position the floor connector bracket and mark a drilling hole. Remove the bracket and drill the floor attachment holes. 12. Position and hang the battery on the wall mount. 13.
  • Page 7 Transport battery 1. Screw in all FOUR handles to the battery frame. Make sure to screw in the handles all the way. 2. Place the battery upright on a dolly and secure it with straps. Stand the battery on the rubber protector only! 3.
  • Page 8 Mounting the Inverter Follow the relevant User Manual to choose a suitable location and correctly mount the Inverter to the wall using appropriate fasteners and with regards to clearance requirements. Diagram of the SolarEdge Genesis inverter mounting below. Mounting AC Isolator Enclosure(s) ISOLATOR ENCLOSURES 1.
  • Page 9 Warning: Before connecting the battery to the inverter, power off the battery. Note: Check the communication cables to ensure the insulation is rated for the highest voltage present inside the switchboard. Additional insulation may be required. Note: If extension of communication cable is required, a female RJ45 joiner may be used to avoid crimping the connector.
  • Page 10 CONNECT TO INVERTER 1. Make sure the inverter is OFF. 2. Connect the DC cables to the DC+ and DC- inputs. Observe correct polarity. 3. Install the SolarEdge Home Network plug-in and antenna in the inverter. 4. Connect cables to the inverter. POWER ON AND ASSOCIATE 1.
  • Page 11 Cover an unused power supply ports with protective covers. Ensure the polarity of the cables is correct to prevent any fuses from blowing. NOTE: A DC circuit breaker is ‘in-built’ within the Battery unit. No additional external DC circuit breaker is required.
  • Page 12 DC input. Power Optimisers - If there are two or more PV arrays, combine their DC cables into a single home run cable. SolarEdge Home Batteries - When installing two SolarEdge Home Batteries, use branch connectors (available from Solahart).
  • Page 13 As the inverter's Connection Unit has a single DC input, crimp together the DC cable from the Power Optimisers along with the batteries into one bootlace ferrule, terminating within the DC port of the inverter. Backup interface (only available for Energy Hub inverters) Read this before installing or operating the Backup Interface.
  • Page 14 Connect Backup Interface...
  • Page 15 1. Turn off connection to grid by switching off the main circuit breaker. 2. Thread the L1, Neutral and Ground wires from the Main Service panel through the supplied ferrite bead. Connect the wires to the L1, Neutral and Ground terminals. 3.
  • Page 16 Commissioning Warning: Before turning on the battery, please ensure that: 1. The equipment is levelled and installed firmly in a place where is convenient for operation and maintenance. The installation place is clean and well ventilated. 2. The ground cable, power cables, communication cables and terminal resistance are connected correctly and securely.
  • Page 17 Configure installation 1. Run SetApp. 2. Scan the QR code on the inverter. 3. Follow the on-screen instructions For post-installation settings, see Connection and Configuration application note. The battery operation is managed by the SolarEdge inverter connected to the battery. Configure installation The purpose of the battery self-test is to check the battery's charge and discharge functionality.
  • Page 18 Note: Ensure firmware is updated as part of commissioning process of the Battery. Monitoring Platform (Mandatory) The Solahart warranty is conditional upon the Energy Bank being connected to the SolarEdge Monitoring Platform (via an internet connection) for the entire duration of the Warranty Period.
  • Page 19 The purpose of labelling is to clearly indicate that the electrical installation has multiple supplies and which circuits are affected by these supplies. Labelling also identifies the components that isolate the various supplies. The following table details labels that are supplied for Solahart Battery Systems. Description...
  • Page 20 Prominent position on main White text on switchboard adjacent to red background Inverter location label Black text on Next to meter white background Black text on Battery D.C. Circuit white background Breaker Black text Inverter AC isolator (If required) white background White text Inverter main switch in switchboard...
  • Page 21 Black and white text with Prominent position symbols on adjacent to the Battery white background Black text Prominent position adjacent to the Battery white background Black text on yellow Prominent position background adjacent to the Battery Black text on yellow On every single Battery background Module...
  • Page 22: Final Checklist

    □ Ensure the customer has access to monitoring portal. □ Complete the Solahart Warranty Registration and Installation Checklist and submit to Solahart. If Backup loads are connected: □ Inform the customer if an AC changeover switch is installed on the Backup panel and demonstrate its functions.

This manual is also suitable for:

Se5000hSe6000hSe8250hSe10000hSe4000h