Page 1
Installation Instructions Single-Phase PV Systems Solahart PV Systems must be installed and serviced by a suitably qualified person.
Page 2
It is also important to observe relevant local codes and regulations for health and safety and accident prevention. Only Solahart parts and Solahart approved parts may be used. No substitute parts may be used without prior approval from Solahart Industries Pty Ltd. Only parts supplied by Solahart Industries Pty Ltd are covered by the Solahart warranty.
Design Dead Load and Live Load at each mounting point. Ensuring only parts supplied by Solahart Industries and installer supplied parts as specified by Solahart Industries are utilised (substitution of parts may void the warranty and invalidate certification). ...
Page 5
DISCLAIMER OF LIABILITY AND WARRANTY Solahart assumes no responsibility for loss, damage or expense resulting from improper installation, handling or misuse of PV modules. Refer to “Solahart PV System Warranty - Australia Only” on page 53 for full warranty terms and conditions.
Strings Rating String Inverter (W) * UNO-DM-2.0-TL-PLUS-B 2240 Check Voltage SB1.5-1VL-40 1960 Tables on page 9 SB2.5-1VL-40 3080 REC290TP2 Modules Max No Min No Max No of System (A)* Inverter Modules No of Modules Power (V)* Modules per String Strings...
Page 7
PVI-3.0-TL-OUTD 3920 Voltage PVI-4.2-TL-OUTD 5600 Tables on PVI-5000-TL-OUTD 5880 page 9 UNO-DM-3.3-TL-PLUS-B 4200 UNO-DM-4.0-TL-PLUS-B 5320 UNO-DM-5.0-TL-PLUS-B 6440 REC290TP2 Modules Max No of Min No Max No of System (A)* Modules Inverter Modules No of Power (V)* Modules per String Strings...
Page 8
Modules per String Strings Inverter (W) * (A)* (V)* SE5000 6440 19.5 SE5000-xxxxxxx ** SE5000H 6440 13.5 REC290TP2 Modules Max No of Min No Max No of Modules Max System Inverter Inverter Inverter Modules No of Power Rating Current Voltage...
Page 9
No of Modules per String of the String 117.6 352.8 156.8 431.2 235.2 470.4 274.4 509.6 313.6 of REC290TP2 = 38.8V REC290TP2 No of Modules of the No of Modules per of the per String String String String 116.4 349.2 155.2...
Earth wires must be sized in accordance with requirements set out in Earthing and bonding arrangements of AS/NZS 5033. Solahart approved earthing plates may be used to earth modules via the racking, instead of wiring directly to the module frames. Refer to “Earthing” on page 31 for more information.
INSTALLATION PROCEDURE Planning – Design the system and layout. Refer to “Planning” on page 12. Determine the spacing of the Rail Supports using the “Maximum Rail Support Spacing Tables” on page 18 and considering the following factors (refer to “Planning” on page 12): Wind Region Terrain Category Roof Type...
PLANNING INSTALLATION TOOLS 4,5 & 6 mm Allen keys or 4,5 & 6 mm Allen Key fittings to suit torque adjustable drill (for racking components and inverter) Torx T20 screwdriver (ABB inverter systems only) Cordless torque adjustable drill ...
Page 13
PLANNING installed at the roof angle for simplicity of installation and appearance, however, if inclination varies by ±15º or more from the correct inclination, performance losses of 4% or more will occur. Modules should be inclined at an angle of at least 10° to support the self-cleaning function of the glass.
Page 14
PLANNING TERRAIN CATEGORY The terrain over which the approaching wind flows towards a structure must be assessed on the basis of the following category descriptions: Terrain Category 2: Open terrain, including grassland, with well-scattered obstructions having heights generally from 1.5 m to 5 m, with no more than two obstructions per hectare, e.g. farmland and cleared subdivisions with isolated trees and uncut grass.
Page 15
PLANNING Use the following diagram, tables and worked example to determine the minimum required roof area for the array when designing and installing with REC280TP modules. REC280TP spacing and dimensions Worked Example: Number of rows: 2 Number of modules per row: 10 Total number of modules = 20 Calculating H: ×...
Page 16
PLANNING Use the following diagram, tables and worked example to determine the minimum required roof area for the array when designing and installing with REC290TP2 modules. REC290TP2 spacing and dimensions Worked Example: Number of rows: 2 Number of modules per row: 10...
RACKING OVERVIEW OF RACKING COMPONENTS Overview of components for tile roof Rail Rail splices Tile roof Z-modules with Wood screws M6 Interfaces (b) Allen head bolt x 80 Overview of components for metal roof Rail Rail splices Metal roof Z-modules with Wood screws M6 interfaces (b) Allen head bolt...
Page 18
RACKING RAIL SUPPORT SPACING Use the following tables to determine the rail support spacing for the relevant roof type based on the previously determined wind region, terrain category, roof position area (Edge Zone or Centre Zone) and maximum height of the installation. MAXIMUM RAIL SUPPORT SPACING TABLES Wind Region A Terrain Category...
Page 19
Rails should be spaced so that the module is clamped in the correct positions. In general, the rails may be spaced between 833 mm and 1249 mm apart for REC280TP modules and 843 mm and 1259 mm apart for REC290TP2 modules. Rail Spacing: REC280TP: 833 –...
Page 20
RACKING TILE ROOF INSTALLATION Note: The tile roof interface is only suitable for installation on timber rafters. 1. Determine and mark the position of the tile roof interfaces according to your plans. Remove the roof tiles at marked positions or, if possible, simply move the tiles up slightly.
Page 21
RACKING 6. For thin tiles (such as slate, shingles), a portion of tile must be cut and removed from the tile above the tile roof interface, creating a recess. Suitable flashing must then be installed around the tile roof interface, with an overlap of at least 150mm at the edges of the recess.
Page 22
RACKING TILT LEG INSTALLATION Note: Screws supplied with the tilt legs are wood screws suitable for timber only. Screws used in metal purlins must be suitable for metal structures and have a TPI (threads per inch) of 14. 1. Determine and mark position of feet according to your plans.
Page 23
RACKING RAIL INSTALLATION 1. Install rails onto the roof interfaces. If the assembly consists of rails of different lengths, always begin with the shortest piece. Install the rail loosely onto the roof interfaces using the Allen head bolt, washer, retaining washer and Z-modules supplied (2 to 3 turns of the bolt are adequate for loose installation).
ROOFTOP ISOLATOR When installing the rooftop DC isolator, a Solahart Rooftop Isolator Subassembly must be used and must be mounted to the rail by following the steps below. To help prevent UV degradation, the Rooftop Isolator Subassembly should be mounted as far from the north side of the array as possible.
(i.e. do not connect or disconnect plug connectors under load conditions). Only use plug connectors supplied with your Solahart PV system, or which are the same type/model and from the same manufacturer as those on the PV module. Ensure that all plug connectors and plug wiring are in good electrical and mechanical condition and are not subjected to mechanical stress.
Page 26
WIRING DC ISOLATOR WIRING The DC isolators utilised in Solahart PV Systems are not polarity sensitive (non polarised type) however for uniformity they should be wired as shown in the DC isolator wiring diagram below. Warning: DC isolator terminal screws must be tightened by hand only. Do not use power tools.
Determine and mark the power optimizer mounting locations on the rail: a. Power optimizers should be spaced approximately 1009 mm (for REC280TP) or 1015mm (for REC290TP2) apart on the rail. See figure below. b. Power optimizers must be positioned so that they maintain a 25 mm clearance distance between the power optimizer and other surfaces to allow for heat dissipation.
Page 28
POWER OPTIMIZERS (SOLAREDGE ONLY) Attach each power optimizer to the mounting rail using the Z-module assembly provided in the BOS kit. See figure below. Apply a tightening torque of 9.5 Nm. Z-module assembly Note: It is recommended that the power optimizers be placed face down to ensure clearance between the back of modules and power optimizers.
Page 29
POWER OPTIMIZERS (SOLAREDGE ONLY) Ensure the Rooftop DC Isolator is in the OFF position, strip 12 mm of insulation from the end of each extension lead and connect the two extension leads to the Rooftop DC Isolator terminals. The Rooftop DC Isolator should be wired in a consistent manner.
The Solahart mounting system requires the use of modules of equal thickness for correct clamping. Note: Ensure only modules of the same type (model & thickness) are clamped side-by-side and electrically connected.
Page 31
PV MODULES The following procedure should be adhered to whilst wiring module strings to prevent the risk of electric shock or inadvertent short circuiting of live cables whilst wiring the Rooftop DC Isolator: Two extension leads per string should be constructed using the DC extension cable provided in the BOS Kit.
Page 32
PV MODULES Warning: Only Solahart approved earthing plates are to be used. Warning: Module frames must be located on top of earthing plate earth bond protrusions. Warning: Earthing plates are intended for single use only and must not be reused.
Page 33
PV MODULES Module Mounting Procedure 1. Mid clamps and end clamps can be inserted into the rail by following the procedure shown, making sure the spring washer is correctly in place. For easy use of Z-modules, ensure Allen head bolt threads do not project through lower side of Z-module, so the Z-module is free to move along the rail.
Page 34
PV MODULES 7. Place an end clamp into the end of each rail. Ensure that the end clamps are tight against the module and are at least 25 mm from the rail ends. In positions where earthing plates are required, ensure the frame of module is located on top of the protrusions of the earthing plate.
INVERTER For inverter installation instructions and warranty exclusions refer to the documents supplied with the inverter. The following points must also be observed when installing the inverter: Warning: Inverters have masses between 9 kg and 27 kg. Proper safe handling procedures must be employed when installing or handling these inverters.
Page 36
INVERTER Inverter Model Maximum AC Fault Current (A) SB 1.5-1 VL-40 12.0 UNO-DM-2.0-TL-PLUS-B 12.0 SB 2.5-1 VL-40 19.0 PVI-3.0-TL-OUTD 16.0 SB3.0-1AV-40 29.0 UNO-DM-3.3-TL-PLUS-B 16.0 SB4.0-1AV-40 29.0 UNO-DM-4.0-TL-PLUS-B 19.0 PVI-4.2-TL-OUTD 22.0 PVI-5000-TL-OUTD 32.0 SB5.0-1AV-40 29.0 UNO-DM-5.0-TL-PLUS-B 24.0 SE5000-xxxxxxxxx* 27.0 SE5000H 23.0 *This model may have suffixes indicating different options and functionality.
Page 37
SolarEdge Wi-Fi kit or integrated Ethernet 4. External alarm – Audible or Visual Alarm Some Solahart inverters can switch a relay when an earth fault is present. The relay can be connected to an audible or visual alarm that meets AS/NZS 5033 requirements. ...
Page 38
4. During the commissioning procedure, you will be asked to insert Aurora Vision access credentials. Please enter the login credentials supplied by the Solahart dealer or create a new profile for the PV system owner.
METER (SOLAREDGE ONLY) Note: The meter is an optional accessory for use in battery systems and for zero export requirements. MOUNTING Warning: Protect the meter from temperatures below -30 C or above 55 C, excessive moisture, dust salt spray, or other contamination, using an IP rated enclosure if necessary Warning: Meter must be installed in an electrical service panel, an enclosure or a limited access electrical room.
Page 40
METER (SOLAREDGE ONLY) SETTING DIP SWITCHES 1. Set DIP switches on the meter as described in the figure below. WIRING AT INVERTER 1. Remove the seal from one of the openings in the communication gland #2 at the bottom of the inverter and insert the RS485 wires from the meter through the opening.
Page 41
METER (SOLAREDGE ONLY) 3. Connect the wires from the meter. a. If you have a SolarEdge branded meter, connect as illustrated below: 4. If the SolarEdge device is at the end of the RS485 bus, terminate the inverter by switching a termination DIP-switch inside the inverter to ON (top position).
If the PV system is directly connected to a distribution board, additional labels must also be placed on the main switchboard and all intermediate distribution boards. The following table details labels that are supplied in Solahart PV Systems. Label...
Page 43
Distribution board number to be entered by installer i.e. DB1 Prominent position adjacent Black and white to the inverter Black text Added below the shutdown sign (Solahart PV Operating yellow background Procedure) Black text Prominent position adjacent to the inverter yellow background...
COMMISSIONING Systems must be commissioned according to AS/NZS 5033. Commissioning tests are required to ensure that the system complies with the aforementioned standard. Commissioning information is provided here as a guide only and it is the installer’s responsibility to ensure that the requirements of AS/NZS 5033 are met. A copy of the relevant commissioning documents must be provided to the owner and a copy kept by the installer.
Page 45
COMMISSIONING SOLAR ISOLATION DEVICE(S) TEST – ROOFTOP DC ISOLATOR(S) This test is performed to ensure the Rooftop DC Isolator(s) are isolating the string(s) from the inverter when in the OFF position. Ensure that the Inverter AC Isolator(s) are in the OFF position. Switch all string DC Isolators to the ON position (Rooftop and Inverter DC Isolators).
Page 46
Warning: Do not turn on the inverter until all of the previous commission procedure tests/checks have been satisfactorily completed. Turn on the PV system (refer to “To Turn PV System On” in the Solahart PV Systems Owner’s Guide) then commission the inverter according to the commissioning procedure described in the relevant inverter installation guide for the model inverter installed.
Page 47
COMMISSIONING ABB DM-PLUS-B series inverters can be commissioned either using the buttons and inverter LED screen or through the inverter Built-in Wifi Web User Interface (UI). For details refer to ABB instruction “Quick Installation Guide UNO-DM-1.2/2.0/3.3/4.0/4.6/5.0-TL-PLUS”. For SMA inverters that do not have display screens, commissioning is performed by directly connecting a smart device to the Inverter Built-in WLAN Web User Interface (UI).
Page 48
COMMISSIONING Configuring Inverter Settings Once logged in, select ‘Configuration with Installation assistant’. If internet is available, configure the network connection: a. Choose appropriate connection type Ethernet WLAN b. Type in network password as required. c. Select ‘Save and Next’. Select correct Time Zone based on installation location.
Page 49
COMMISSIONING ABB INVERTER START VOLTAGE The start voltage (VStart) is the DC voltage at which the inverter will begin to transform DC to AC. Inverter Model UNO-DM-2.0-TL-PLUS-B UNO-DM-2.0-TL-PLUS-B only has one MPPT with a nominal factory start voltage of 150V. If fewer than 5 modules are connected, the start voltage must be adjusted down in order for the system to function.
Page 50
Indicative String V @ STC* Number of modules in string REC280TP modules REC290TP2 modules 353.1 * Values measured at standard test conditions (STC) defined as: irradiance of 1000 W/m , Spectrum AM 1.5, and cell temperature 25ºC. Variations from STC values will affect actual V...
Limited Warranty. Solahart, in addition can provide preventative maintenance and advice on the operation of the PV System. You can contact Solahart on 1800 638 011 to arrange a service call or to find out details about this warranty.
Page 54
There are many factors that affect the output of your Module. Solahart does not warrant a specific power output for your Modules. All modules degrade over time and power output is subject to many variables including the age of the Module.
Page 55
The date of installation of the Power Meter. Remedies If Solahart determines that a reported defect in relation to a Product is eligible for coverage under this Limited Warranty (including retention capacity), Solahart will, at its sole option: Repair the defective Product;...
Page 56
Warranty coverage for labour – PV System and LG Chem Battery In addition to the above coverage, Solahart provides you with five (5) years of coverage, from the date of installation, for all labour costs involved with inspection by Solahart, removal or installation of warranted parts or components by Solahart of your PV System.
Page 57
If your claim relates to a failure to operate in accordance with the Solahart Owner’s Guide and Installation Instructions as a result of one of the factors listed above, Solahart may charge you at its standard rates for its time and materials related to your claim.
Page 58
Solahart is liable under applicable mandatory laws. If you require a call out and we find that the fault is not covered by Solahart's warranty, you are responsible for our standard call out charge. If you wish to have the relevant component repaired or replaced by Solahart that service will be at your cost.
Page 59
SOLAHART PV SYSTEM WARRANTY - AUSTRALIA ONLY Exhibit A LG CHEM CAPACITY RETENTION LEVELS References in this Exhibit to the “Product” are to a LG Chem Battery. The Product will retain at least 60% of Nominal Energy* when the Product is operated under normal use,...
Page 60
Solahart Industries Pty Ltd (A.B.N. 45064945848) For SERVICE Telephone - 1800 638 011 Registered Office or your nearest Solahart Dealer 1 Alan Street (PO Box 7508, Silverwater, 2128) For Sales Telephone - 1300 769 475 Rydalmere New South Wales 2116 or your nearest Solahart Dealer www.solahart.com.au...
Need help?
Do you have a question about the REC290TP2 and is the answer not in the manual?
Questions and answers