Installation Manual BM-8-906
Mounting Kit
General
Please read this BM-8-906 Mount installation manual carefully in order to profit fully from the load cell
application.
Take care that the mounts and load cells are applied within their specifications. Certainly during installation,
special attention should be paid to exceptional forces exceeding these specifications.
Install the mount(s) in such a way that all bottom plates are at the same level and in the same horizontal plane.
The same goes for the top plates. Always check that the load cell and/or mount are not loaded with forces
exceeding their specifications.
If large load displacements can be expected, stay rods should be applied in order to limit uncontrolled side forces.
Always use shim plates to align mounts in the same horizontal plane and level.
Routine maintenance includes the optical inspection of bolts, plates and force bearing parts, as well as the removal
of dirt, dust and debris built up near or between the load cell and/or mount in order to let it move freely.
Capacity
0.15 – 2t
2.5 – 5t
Dimensions:
Description
Top Plate
Bottom Plate
Total Height
Hex Bolt for load cell fastening
Hex Bolt for adjusting lift off protection
Hex Bolt for lift off protection
Hex Bolt for transport plate/earthing cable fastening
Note: Please refer to the parts list on page 5 for an overview of all parts of the mount.
Specifications and dimensions are subject to change without notice and do not constitute any liability whatsoever.
Nr. 2022.11 Installation Manual BM-8-906 Rev2
Page 1/5
Working height
120 mm
4.72 inch
145 mm
5.71 inch
Installation height
120 mm
4.72 inch
145 mm
5.71 inch
Dimensions 0.15 – 2t
140mm x 120mm
200mm x 120mm
120mm
M12 x 70
M8 x 20
M16 x 20
M8 x 12
Mounting torque load cell
100 Nm
74 Lb ft
450 Nm
332 Lb ft
Dimensions 2.5 – 5t:
150mm x 150mm
240mm x 150mm
145mm
M18 x 80
M8 x 20
M16 x 20
M8 x 12
Zemic Europe B.V.
T: +31 76 50 39480
info@zemic.nl
www.zemiceurope.com