3.3 Installation- General Procedure:

Install the Master Control Station system first 
(The exact sequence of Sirens/Solar Panels/Station 
housing  for each site is not critical and can be
co‐ordinated at the installers discretion)
Peform Systems check on each station
as they are installed
Install Slave Control Stations 
one at a time, working away 
from the Master Station
Validate system functionality 
and performance
Finalise installation of each 
Control Station
Perform acceptance test and 
WiLAS Installation & User Guide
"sign‐off"