Miura MTU-100 UL Engineering, Installation And Service Manual
Miura MTU-100 UL Engineering, Installation And Service Manual

Miura MTU-100 UL Engineering, Installation And Service Manual

Multiple installation online communication (mom)

Advertisement

Multiple Installation Online Communication
(MOM)
ENGINEERING, INSTALLATION
& START UP MANUAL
MIURA BOILER CO., LTD.
* INFORMATION IN THIS MANUAL MAY BE CHANGED WITHOUT NOTICE.
O
.
WNER SHALL MAINTAIN THIS MANUAL IN LEGIBLE CONDITION FOR FUTURE REFERENCE
Revised: 03 July 07

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the MTU-100 UL and is the answer not in the manual?

Questions and answers

Summary of Contents for Miura MTU-100 UL

  • Page 1 Multiple Installation Online Communication (MOM) ENGINEERING, INSTALLATION & START UP MANUAL MIURA BOILER CO., LTD. * INFORMATION IN THIS MANUAL MAY BE CHANGED WITHOUT NOTICE. WNER SHALL MAINTAIN THIS MANUAL IN LEGIBLE CONDITION FOR FUTURE REFERENCE Revised: 03 July 07...
  • Page 2: Table Of Contents

    TABLE OF CONTENTS Specifications......................1 Installation......................2 2.1 Mounting..........................2 2.2 Wiring ..........................3 2.2.1 MTU Wiring ....................... 3 2.2.2 Network Wiring ......................4 3 Designated Communication Cable..............5 Setting and Initialization (Before communication test) ........6 4.1 Boiler (XJ1) Setting and Initialization ................7 4.2 Boiler (BL11) Setting and Initialization................
  • Page 3: Specifications

    • Name of the unit: MI online communication interface unit • Model: MTU-100 UL • Manufacture: Miura Boiler Co., Ltd. • Boiler models: EX, EXH, EXN, LX, LXL, and LXH series • Connection: Boilers ---------one net work (in-line connection) Telephone line ------- dedicated line [Analog phone line] •...
  • Page 4: Installation

    2 Installation 2.1 Mounting MTU-100 UL is a single wall mounted unit. The master panel communicates with each individual boiler Multiple Installation communication board, model MA2-901 that is installed by the factory in each boiler, by a simple twisted pair network.
  • Page 5: Wiring

    2.2 Wiring 2.2.1 MTU Wiring Do not remove the end resistor! To the closest boiler’s MA2 Board terminal in the daisy chain. (N0, N1, N2) Please see follow page for details. MTU-100 XG1 Board Boiler MA2 Board A0 ←→ N0 A1 ←→...
  • Page 6: Network Wiring

    2.2.2 Network Wiring (MTU ~ the Boilers) Do not remove the end resistor from the last boiler on daisy chain ! Boiler MA2 Board MTU-100 MA2(Left) and XG1(Right) Board...
  • Page 7: Designated Communication Cable

    3 Designated Communication Cable The designated communication cable must be used. If the cable is not the designated one, it can cause communication interference. [Designated communication cable] Use shielded – twisted pair cable 2P (two pair) AWG-20 as communication cable.
  • Page 8: Setting And Initialization (Before Communication Test)

    4 Setting & Initialization (Before communication test) After proper installation, MOM (MIURA Online Maintenance) needs to be set and initialized properly. There are three physical pieces of hardware that has to be programmed to make the system work – 1) the XJ1 / BL11 setting in the boiler panel 2) the MA2 board on each boiler, and 3) the MA2 board on the MTU.
  • Page 9: Boiler (Xj1) Setting And Initialization

    4.2 Boiler (BL11) Setting and Initialization. 1- Turn the ‘Function Select’ switch to ‘on’ (upwards). TTL1 PORT - MA2 / MODEM CONNECTION FUNCTION SWITCH DIP SWITCHES BL11 CPU 2- Press the ‘Data’ button to scroll to as under:- MAINTENANCE MODE CHANGE DATA DATE SPEC SET MODE DATA1 SET MODE...
  • Page 10: Boiler Id Setting And Initialization

    4.3 Boiler ID Setting and Initialization. Each boiler has to have ID number. Set the ID number on MA2-901 board which is mounted in the boiler control cabinet. MA2 Board in the boiler control box. For example > if there are 5 boilers, set as follows: Boiler #1 ……...
  • Page 11: Boiler Ma2 Setting And Initialization

    4.4 Boiler MA2 Setting and Initialization Set DIP-SW (SW3/SW4) on MA2 board in the boiler cabinet as follow: MA2 Board in the boiler control box. After you change the setting, turn SW3-7 to “ON” then turn SW3-8 to “ON” for one second and turn SW3-8 to “OFF”, then turn SW3-7 to “OFF” to initialize.
  • Page 12: Mtu-100 Ma2 Setting And Initialization

    4.5 MTU-100 MA2 Setting and Initialization Connect the modem to an analog phone line and set DIP-SW (SW3/SW4) on MA2 board in the MTU-100 unit as follow: MA2 Board (Left) in the MTU-100 1. After you change the setting, turn SW3-7 to “ON” then turn SW3-8 to “ON” for one second and turn SW3-8 to “OFF”, then turn SW3-7 to “OFF”...
  • Page 13: The Points Of Communication Wiring

    " " # " 1. The telephone line must be a dedicated, analog line. Never “Assume” it is. Connect a telephone to the phone jack and call 1-847-465-0001(Chicago office) or 1-519-758- 8111(Canada) to make sure there is no “9” or code required to dial out. We can accommodate a “9”before the number, but we cannot accommodate a dial out code.