Sungrow SBR HV Battery Installation Quick Guide
Sungrow has released high-voltage battery - SBR series (9.6kWh-25.6kWh).
To ensure smooth installation and avoid difficulty on site, please read below checklists and make
sure you are ready before installing SBR HV batteries. If you have any questions, please free to
contact Sungrow team (1800 SUNGROW (786 476) service@sungrowpower.com.au) before
asking help onsite to reduce urgency.
Check Items
Requirements
•
Manuals
Read
•
Follow the manuals and make sure the operating environment
is suitable for inverter and batteries.
•
Application
Check with the distributors or Sungrow team for technical advice
of off-grid application or any other complex scenarios (click here)
•
Battery parallel application will not be available until Q3 2021 and
the exact date is to be informed by Sungrow.
•
Remote
If it is the first installation of HV battery system, Sungrow advises
Support
installers to book the time for remote support. Our team will
deliver support when you are on site to avoid any difficult to
reach us.
Remote Area •
Installers need to be cautious for the remote installation.
•
Installer must take responsibility of the after-sales service.
•
Sungrow technical support will be limited if the battery systems
are installed remote areas with no local electrician for service
(click
•
Internet
The system needs to operate with Internet available. otherwise,
Sungrow's support will be limited and less efficient.
•
If there is no Internet connection, please contact the distributors
to purchase 4G dongle for internet access.
Cables/Tools Prepare tools and cables prior to the installation.
•
DC power cables≥ 11AWG (DC
with the insulation compliant to Australia Standard.
•
Earth cables ≥ 13AWG (4mm
•
Tools to make Ethernet cable with RJ45 terminal.
•
The latest version of iSolarCloud is necessary to be installed on
mobile or tablet prior to the commissioning and firmware
upgrading.
Comm. Cable •
Long cables (>10 m) could cause communication failure
between the inverter and battery.
•
It's installer's responsibility to conduct communication
cable continuity test before contacting Sungrow team
•
Tips
Follow the installation tips & commissioning tips from the 2nd
page of this document
GD_202111_Sungrow SBR HV Battery Installation Quick Guide with SHRT _V3.0
As we continuously improving our services, changes to this document may occur without notice.
Sungrow product manuals
here
for remote area policy)