Advertisement

Quick Links

O
T I M U S
Gateway
S O R T E R S
Installation manual
Taylor Technologies BV
Torenallee 32-14
5617 DB Eindhoven
The Netherlands
tel: +31 (0)85 107 1871
mail: support@taylor.solar
web: www.taylor.solar
2022-012-R-0017-A2_Draft 4
1

Advertisement

Table of Contents
loading

Summary of Contents for Taylor TAYLOR-GTW-2A

  • Page 1 T I M U S Gateway S O R T E R S Installation manual Taylor Technologies BV Torenallee 32-14 5617 DB Eindhoven The Netherlands tel: +31 (0)85 107 1871 mail: support@taylor.solar web: www.taylor.solar 2022-012-R-0017-A2_Draft 4...
  • Page 2: Table Of Contents

    T I M U S Gateway S O R T E R S Table of contents About this document...................2 1.1 Purpose of this document................2 1.2 How to use this document................2 1.3 Language......................2 1.4 Symbols and signal words used in this document........2 Safety......................3 2.1 General........................3 2.2 Connect to the inverter..................3...
  • Page 3: About This Document

    T I M U S Gateway S O R T E R S 1 About this document 1.1 Purpose of this document This document is only applicable for the gateway. Refer to the technical specifications for the applicable part numbers. From here on, this document refers to the gateway as the equipment.
  • Page 4: Safety

    - The gateway is designed to apply within the Taylor system, do not use it for any other purposes. - Use the equipment only in combination with inverters that are approved by Taylor.
  • Page 5: Packaging

    T I M U S Gateway S O R T E R S 3 Packaging A. Gateway B. Installation manual C. Power cable D. Fastening materials E Drill template 2022-012-R-0017-A2_Draft 4...
  • Page 6: Description

    G. PV cable feed-through hole H. Cable clamp I. Power switch with indicator light J. Identification plate K. Datacable L. Cap 4.3 Data cables delivered seperate from gateway Data cable Part number (P/N) To use with this inverter TAYLOR-GTW-C-00 Goodwe TAYLOR-GTW-C-SL Solis 2022-012-R-0017-A2_Draft 4...
  • Page 7: Status Shown By The Indicator Light In The Power Switch

    T I M U S Gateway S O R T E R S 4.4 Status shown by the indicator light in the power switch Indicator light in the Status of Remarks power switch the gateway The system produces energy. The cable from the solar string is energized.
  • Page 8: Installation

    T I M U S Gateway S O R T E R S 5 Installation 5.1 Preliminary requirements Scan the barcode of each individual solar panel. In the onboarding application on your mobile device, On the 'Scan' screen (A), select the 'Scan' button (B).
  • Page 9: Install The Gateway

    T I M U S Gateway S O R T E R S 5.2 Install the gateway. Warning: Obey the safety instructions of the inverter. Make sure that the inverter is off and de- energized. Do not connect more than one string of solar panels to a MPPT connection.
  • Page 10 Connect the cables to the inverter (D). Refer to the documentation of the inverter Connect the data cable to the inverter (B). Refer to the website: www.taylor.solar > Downloads > Manuals. Connect the data cable to the data connection (A). 2022-012-R-0017-A2_Draft 4...
  • Page 11 12. On the 'launch' screen (A), select the XXXXXXXXXXXXXXXXXXXXX 'launch' button (B). When the system onboarding is confirmed, the customer XXXXXXXXXXXXXXXXXXXXXX receives an e-mail to register to the XXXXXXXXXXXXXXXXXXXXXX XXXXXXXXXXXXXXXXXXXXXX Taylor dashboard. XXXXXXXXXXXXXXXXXXXXXX XXXXXXXXXXXXXXXXXXXXXX XXXXXXXXXXXXXXXXXXXXXX XXXXXXXXXXXXXXXXXXXXXX XXXXXXXXXXXXXXXXXXXXXX XXXXXXXXXXXXXXXXXXXXXX XXXXXXXXXXXXXXXXXXXXXX 13. Set the switch (A) in the on position.
  • Page 12: Declaration Of Conformity

    S O R T E R S Declaration of conformity Hereby, Taylor Technologies B.V. declares that the radio equipment type TAYLOR-GTW-2A is in compliance with Directive 2014/35/EU. The full text of the EU declaration of conformity is available at this internet address: www.taylor.solar/declaration.
  • Page 13 T I M U S Gateway S O R T E R S Power Output Model SYS1308-2412-W2E adapter Min. Load Max. load 2 A ±5% 3.5~5.5 A 14~16 V Efficiency >70% Max. power 24 W Ripple & N 120 mV Overvoltage category input...
  • Page 14 T I M U S Gateway S O R T E R S Hold-up Time 10ms @ AC nominal Input and Output full load MTBF > 35K hours Qualification DC cable & Standard length of the cable connector 1,8m & It depends on customer requirements and upon specifications Efficiency...
  • Page 15: Gateway

    T I M U S Gateway S O R T E R S 7.2 Smart module Cell-stringoptimizer: CSO-72 Input Cell-string (3 per module) Input MPP voltagerange 7.5Vdc – 20Vdc Rated for solar PV moduleswith max. Voc at lowest temperature Rated for solar PV moduleswith max. Impp at 11.5 Output operational mode Cell-string (3 per...
  • Page 16 T I M U S Gateway S O R T E R S General data Operatingtemperaturerange junction box -40 °C / +85 °C Output wire 2x 1.2 m 4mm2 (standard configuration) Connectors MC4 (standard configuration) Overvoltage category Pollution degree Pollution 1 for potting part Pollution 2 for non-potting part Degree of protection P65/IP67...
  • Page 17: Drill Template

    S O R T E R S Drill template Drill/Screw here 85 mm Drill Template taylor. P/N: 2021-012-D-0003 CAUTION: Measure the control line (X). If the control line is not 100 mm, do not use this drill template. Do not drill or screw in electricity lines, water pipes, and such items.
  • Page 18 T I M U S Gateway S O R T E R S 2022-012-R-0017-A2_Draft 4...