Instruction book
5
Operating instructions
5.1
Initial start-up
Safety
Procedure
1. Consult the sections Electric cable size, Installation proposal and Dimension drawings
2. The following transport fixtures (1), painted red, must be removed:
3. Check that the electrical connections correspond to the local codes and that all wires are clamped tight to
their terminals.
The installation must be earthed and protected against short circuits by fuses of the inert type in all phases.
An isolating switch must be installed near the compressor.
4. Check transformer for correct connection (CPT1). Check the settings of drive motor overload relay (OL1).
2012 2039 28
The operator must apply all relevant Safety precautions.
For the position of the air outlet and the drain connections, see sections Introduction.
Transport fixtures
99